CERC · Central Electricity Regulatory Commission
Measures to Relieve Congestion in Real Time Operation Regulations, 2009 — Corrigendum, 2010
Corrigendum (04-02-2010)
CorrigendumDated 4 Feb 2010No. L-7/139(159)/2008-CERC dated 4th of February, 2010
Corrects the Measures to Relieve Congestion in Real Time Operation Regulations, 2009.
Summary
Summary written by software. Check the regulator's original before you rely on it.
A one-page CERC corrigendum dated 4 February 2010 (p1) correcting two passages of the CERC (Measures to relieve Congestion in real time operation) Regulations, 2009. Item 1 substitutes a mis-stated term in Regulation 2(1)(c): 'Available Transmission Capability' becomes 'Available Transfer Capability' (p1). Item 2 rewrites Regulation 4(3): the charge is made 'applicable to' rather than 'payable by' grid users, the trigger widens from overdrawal alone to overdrawal, underdrawal, over-injection and under-injection, and the money flow becomes 'payable/receivable' (p1). Although styled as corrections, these change who is charged and on what, so anyone reading the 2009 congestion-relief regime must read them together. The closing Note records that the principal regulations were published on 24 December 2009 in Part III-Section 4 of Gazette of India Extraordinary No. 252 (p1). No Gazette date or commencement is printed for the corrigendum itself.
Read with this
The regulation
Amendments and corrections
Procedures and orders made under it
Other copies of these documents (1)
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.