Skip to content

CERC · Central Electricity Regulatory Commission

RE Tariff Regulations, 2009 — First Amendment, 2010 — Statement of Objects and Reasons

Statement of Objects and Reasons

Statement of reasonsDated 27 Apr 2010No.L-7/186(201)/2009-CERC dated 27.4.2010

Replaced by Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2012

See that regulation for the date it took effect and for anything it keeps in force.

The commission's reasons for the Renewable Energy Tariff Regulations, 2009 or one of its amendments.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Central Electricity Regulatory Commission's Statement of Objects and Reasons, dated 27 April 2010, for the First Amendment to the CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2010. It is an explanatory record of the Commission's reasoning and the stakeholder consultation, not the operative amendment text.

The Introduction (pp1–2) sets out the Commission's legal mandate under the Electricity Act, 2003, including Section 79 functions, Section 61 tariff powers and Section 178(2)(s) regulation-making power with previous publication under Section 178(3). It records the chronology: the original RE Tariff Regulations were notified on 16 September 2009; a draft First Amendment was published on 19 January 2010 for comments; a public hearing was held on 10 February 2010; and the First Amendment was notified on 25 February 2010.

The central discussion (pp2–4) concerns tariff visibility for solar projects. Stakeholders asked for longer control periods for Solar PV and Solar Thermal projects, several linking solar commissioning to the evolving Jawaharlal Nehru National Solar Mission (JNNSM) framework and MNRE draft Phase-I guidelines. The Commission decided that the generic tariff and norms for Solar PV for 2010-11 would also apply to Solar PV projects commissioned during 2011-12, and that the Solar Thermal generic tariff for 2010-11 would also apply to Solar Thermal projects commissioned during 2011-12 and 2012-13. These extensions are conditional: PPAs must be signed on or before 31 March 2011, and the entire capacity must be commissioned by 31 March 2012 for Solar PV and by 31 March 2013 for Solar Thermal (p4).

On zone-wise CUF and solar module degradation (pp4–5), the Commission declines to make changes in this process, citing the absence of a scientific solar radiation atlas and referring to its detailed ruling in the order dated 25 February 2010 in Petition No. 13/2010 (Suo-Motu). The annexure (pp6–8) summarises stakeholder comments on applicability of tariff, module degradation, and global solar insolation/CUF.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff

Read with this

The regulation

Amendments and corrections

Commencement notices and reasons

Other copies of these documents (1)

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document