Wind and Solar Forecasting, Scheduling and Deviation Settlement Regulations, 2019

Tamil Nadu Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement and related matters for Wind and Solar Generation) Regulations, 2019

RegulationDated 1 Mar 2019Published in the Gazette 20 Mar 2019Notification No.TNERC/F&S Wind &Solar/21-1 dated 01.03.2019

Replaced by Forecasting, Scheduling and Deviation Settlement for Wind and Solar Generation Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is TNERC's 2019 principal regulation establishing how wind and solar generators in Tamil Nadu are forecast, scheduled and settled for deviations from schedule. It was issued on 1 March 2019 and published in the Tamil Nadu Government Gazette on 20 March 2019 (p1–2); most provisions take effect from publication, but the commercial-arrangement provisions and the deviation charge/penalty provisions commence six months later (p2).

Regulations 1–2 (p2–3) give the short title, commencement and extent, and define the core vocabulary the rest of the instrument runs on: absolute error, available capacity (AvC), deviation, de-pooling, gaming, pooling sub-station, procurer, QCA, scheduled generation, the State Deviation Pool Account (Wind and Solar) and the State Deviation Pool Account (DSM), State Entity, SLDC and time block.

Part A (p3–4) states the objective — grid integration of wind and solar while preserving grid security — and the applicability rule: all wind and solar generators in Tamil Nadu connected to the intra-State transmission or distribution system, excluding rooftop PV, whether self-consuming or selling within or outside the State. It also commits the Commission to review the regulations, including absolute error, accuracy band and deviation charge, after two years (p4).

Part B (p4–6) is the Forecasting and Scheduling Code. It requires generators at each pooling sub-station to appoint a Qualified Coordinating Agency (QCA), sets out how the QCA is chosen and what it does (registration with SLDC, data, de-pooling, settlement, nodal interface), prescribes Day-Ahead and Week-Ahead schedules in 15-minute blocks, rules on schedule revision, mandates a Detailed Procedure from SLDC with a defined table of contents, and treats gaming — intentional mis-declaration of available capacity — as a breach with a multiplied penalty and possible de-registration.

Part C (p6–8) is the commercial core: deviation settlement for intra-State transactions and for inter-State transactions, the two being accounted separately at each pooling sub-station, plus the annual cap on total deviation charges remitted and the refund mechanism for excess amounts. Part D (p8–10) covers implementation — metering by Special Energy Meter, QCA–SLDC communication, deviation accounting by SLDC, the payment mechanism and payment security, de-pooling, curtailment intimation and energy accounting. Part E (p10) contains the Commission's powers to amend, remove difficulties, relax and issue directions. An Annexure (p11–12) sets the deviation-charge framework for generators connected to the intra-State network but selling or consuming power outside Tamil Nadu.

Standard name
Forecasting, Scheduling and DSM for Wind and Solar
Primary topics
Scheduling and despatch, Deviation settlement (DSM), Energy accounting and settlement

Read with this

Other copies of these documents (1)

2 more documents belong here and are not on Voltaic: 2 copies in another language.

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document