HERC · Haryana Electricity Regulatory Commission
Duty to Supply Electricity on Request and Power to Recover Expenditure and Power to Require Security Regulations, 2016 — 4th Amendment, 2026
Haryana Electricity Regulatory Commission (Duty to Supply Electricity on Request and Power to Recover Expenditure and Power to Require Security) Regulations, 2016 (4th amendment) Regulations, 2026
AmendmentDated 22 Jul 2026Published in the Gazette 29 Jul 2026Regulation No. HERC/34/4th Amendment/2026 dated The 22nd July, 2026
Amends the Duty to Supply Electricity on Request, Recovery of Expenditure and Security Regulations, 2016.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a two-page gazette notification by the Haryana Electricity Regulatory Commission amending its 2016 regulations on the duty to supply electricity on request. It was issued on 22 July 2026 and published in the Haryana Government Gazette of 29 July 2026, from which date it comes into force across the whole state (p1). It forms part of the principal regulations rather than standing alone (p1).
The operative change is a new set of sub-clauses inserted after Regulation 4.8.1 of the principal regulations (p1–2). They govern what a distribution licensee may charge when an existing consumer asks for a reduction in load or contract demand, splitting the case where the voltage of supply is unchanged from the case where supply moves from HT to LT, and giving the consumer the option of being metered at 11 kV or LT after reduction. Processing fee is cross-referred to Regulation 3.6 of the principal regulations subject to a ceiling (p2).
The amendment then creates a three-year settlement period from the date of load reduction, within which the consumer may restore load up to the originally sanctioned level free of service connection charges, with restoration beyond that window treated as a fresh load-extension application; extension beyond the original sanctioned load within the window attracts charges on the incremental load, and the consumer bears metering-change costs (p2).
A proviso attaches conditions: one reduction and one restoration per settlement period; a six-month lock-in after each reduction or restoration; restoration capped at the original contract demand; restoration subject to the licensee certifying system capacity and technical feasibility; and exclusion of consumers with outstanding dues or ongoing theft / unauthorised-use proceedings (p2). It does not restate the principal regulations' wider supply obligations.
Read with this
The regulation
Amendments and corrections
- Dated 19 Mar 2020Duty to Supply Electricity on Request and Power to Recover Expenditure and Power to Require Security Regulations 2016 — 1st Amendment, 2020
- Dated 27 Sep 2023Duty to Supply Electricity on Request and Power to Recover Expenditure Regulations, 2016 — 3rd Amendment, 2023
- Dated 27 Sep 2023Duty to Supply Electricity on Request, Power to Recover Expenditure and Power to Require Security Regulations, 2016 — 2nd Amendment, 2023
Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.