AmendmentDated 19 Mar 2020HERC/ 34/ 2016/ 1st Amendment / 2020 dated The 19th March, 2020

Amends the Duty to Supply Electricity on Request, Recovery of Expenditure and Security Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on herc.org.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the first amendment to HERC's 2016 Duty to Supply Regulations, notified on 19 March 2020 and taking effect from publication in the Haryana Government Gazette, a date the text does not print (p1). It substitutes two provisions, inserts one proviso and restates a third, all in the parent 2016 regulations.

Regulation 4.12.2 is replaced wholesale (p1–2). It sets the framework for a Developer that opts under Regulation 3.10 to build the electrical infrastructure in its own development area: work must go through a licensed electrical contractor; the electrification plan, execution plan and phase-wise cost estimates need prior licensee approval and the Developer pays supervision charges; execution is capped in number of phases and years, with a longer phasing allowed for large development areas and a contiguity condition on each phase. The licensee must issue a demand notice for a bank guarantee in each phase, and the new sub-paragraphs give it remedies — encashing, extending against a larger guarantee, or cancelling the electrification plan and all guarantees — when a phase overruns or the work is non-conforming. Completion is verified and certified, or inspected suo motu, and all guarantees must be irrevocable, unconditional and valid beyond the phase completion period.

A further proviso inserted after Regulation 4.8.1 (p3) deals with when service connection charges are payable for supply through an independent feeder. Regulation 4.8.2(iii) (p3) is replaced so that a utility may connect several applicants to an existing independent feeder where right-of-way or similar problems exist, restricted to HT categories, with metering mandatory at the consumer end. By clause 1.3–1.4 the amendment reaches all Distribution and Retail Supply licensees, including deemed licensees, and all consumers in Haryana, including entities exempted under Section 13 of the Act (p1).

Standard name
Duty to Supply on Request, Recovery of Expenditure and Miscellaneous Charges
Primary topics
New connections and load changes, Connection and miscellaneous charges, Supply to buildings and colonies

Read with this

Voltaic last read HERC's website for final documents on 24 Nov 2026 (2 pages). A document HERC issued after the page that lists it was read may not be held by Voltaic yet.