HPERC · Himachal Pradesh Electricity Regulatory Commission
Himachal Pradesh Electricity Grid Code (First Amendment) Regulations, 2018 — Order on Draft Amendments
In the matter of draft amendments of the Himachal Pradesh Electricity Regulatory Commission Himachal Pradesh Electricity Grid Code (First Amendment) Regulations, 2018.
OrderDated 9 Oct 2018
Replaced by Himachal Pradesh Electricity Grid Code Regulations, 2026
See that regulation for the date it took effect and for anything it keeps in force.
Read with the Himachal Pradesh Electricity Grid Code, 2008.
Summary
Summary written by software. Check the regulator's original before you rely on it.
HPERC issued this order on 9 October 2018 to close out consultation on the draft Himachal Pradesh Electricity Grid Code (First Amendment) Regulations, 2018 (p1, p7). The order is not the amendment itself: it records the public process and the Commission's decisions on stakeholder objections, then directs that the amendment regulations be finalised on those lines and notified (p1, p7).
The recitals state that the Commission notified the principal HP Electricity Grid Code, 2008, published in the Rajpatra on 11 May 2008, and that it invited public objections under Section 181(3) of the Act read with Rule 3 of the Electricity (Procedure of Previous Publication) Rules, 2005 through notices in The Tribune and Dainik Bhaskar on 25 July 2018 (p1). The draft was posted on the Commission's website, and major stakeholders were asked by letter dated 26 July 2018 to respond (p1). Two stakeholders filed objections: the Directorate of Energy and IA Hydro Energy Pvt Ltd (p1–2, p5).
The body of the order is a clause-by-clause disposal table (p2–6). For the Directorate of Energy, the Commission deals with proposed changes to definitions and terms (State Power Grid/State Grid, connected to, RPC/SPC), collective transactions, renewable energy/SSGS, open access consumers as State Entities, drawal schedules and State/STU periphery concepts, commissioning/implementation wording, and SLDC consultation (p2–5). It accepts some suggestions, agrees in principle to others, and rejects or modifies some. For IA Hydro Energy, the table addresses time-block duration, SLDC permission for certain thermal/gas/hydro units, must-run status of hydro plants, revision of declared capability by ISGS/BBMB stations, and scheduling changes by RLDC/State Entities, with references to CERC and PGCIL norms (p5–7).
The order ends by saying the amendment regulations shall be finalised on the above lines and notified accordingly; it is dated 9 October 2018 at Shimla (p7). No final regulation text, Gazette publication date, or in-force date is provided.
Read with this
The regulation
- Dated 5 Aug 2008Himachal Pradesh Electricity Grid Code, 2008
Amendments and corrections
Proposed changes (drafts with no final yet)
- Dated 24 Dec 2025Himachal Pradesh Electricity Grid Code Regulations, 2025 — Draft
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.