MERC · Maharashtra Electricity Regulatory Commission

Commencement of Commercial Arrangement of Deviation Settlement Mechanism Regulations, 2019 — Order, 2021

Commencement of the commercial arrangement of MERC (Deviation Settlement Mechanism and related matters) Regulations, 2019 and related issues thereof

OrderDated 7 Oct 2021

Replaced by Deviation Settlement Mechanism and related matters Regulations, 2026

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Deviation Settlement Mechanism and related matters Regulations, 2019.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken, including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations, shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software, from pages 1 to 25 of 34. Check the regulator's original before you rely on it.

This is MERC's order dated 7 October 2021 on commencement of the commercial arrangement under the MERC (Deviation Settlement Mechanism and related matters) Regulations, 2019 (DSM Regulations). Pages 1–7 set out the chronology: the DSM Regulations were notified on 1 March 2019; commercial implementation was repeatedly deferred amid software and metering readiness issues, COVID-19 and litigation; the Commission's 6 May 2021 suo motu order relaxed volume limits and laid down a stabilisation-period approach; the ATE later allowed withdrawal of TPC-D's appeal (pp1–7). Pages 7–18 summarise the DSM Working Group's 1 October 2021 report on the extended mock trial run (17 May–15 August 2021 and one week 6–12 September 2021): metering migration from Plan B to Plan A, DSM software readiness, entity registration, bill analysis and stakeholder issues, supported by two comparison tables (pp7–18; Tables 1–2 at pp10–11). Pages 18–19 list five issues for clarification and invoke Regulations 1, 19 and 20 of the DSM Regulations (pp18–19). Issue 1, pages 19–22, deals with standby power: settlement for the first three time blocks will be done outside the DSM software, and the causer-pays principle is affirmed for Mumbai generators (pp19–22). Issue 2, pages 22–24, continues relaxed volume limits for TPC-D and AEML-D during stabilisation, concluding that the earlier changeover-consumer adjustment is covered by the broader relaxation already allowed (pp22–24). Page 25 begins Issue 3 on Virtual State Entity scheduling, noting its ancillary nature and that VSE rates are in the Statement of Reasons and can change only by regulation amendment (p25). Issues 4 and 5 — seller deviation under FBSM operation and seller volume limits.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement, Metering

Read with this

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on merc.gov.in ↗

Report an issue with this document