Transmission and SLDC ARR and Tariff Petition Formats

Formats - Transmission

OrderDate not stated

Replaced by Generation, Transmission, Wheeling and Retail Supply Tariff (MYT) Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Terms and Conditions for Determination of Generation, Transmission, Wheeling and Retail Supply Tariff Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a compendium of 45 filing formats — Forms T1 to T45 — for a transmission licensee/STU and SLDC preparing their Annual Revenue Requirement and tariff petition. The opening page lists every form and adds two procedural notes: the petition and calculations must be filed electronically in Word/Excel, and the formats may be amended or supplemented as needed (p1). The body then provides the formats themselves.

The first forms compute the ARR separately for transmission and SLDC business (pp2–3), followed by O&M summary and normative O&M formats (pp4–5). Forms T5–T9 break down employee expenses, employee strength, administration and general expenses, and repair and maintenance for transmission and SLDC business (pp6–10). Forms T10–T12 cover fixed assets and depreciation, SLDC fees and charges, and return on equity (pp11–14). Forms T13–T19 collect loan details, year-wise capital expenditure, capital works in progress, interest and finance charges, prior-period income/expenses, capitalised expenses, and write-offs (pp15–22). Forms T20–T23 describe the transmission utility’s key characteristics, normative parameters, transmission capacity and energy balance (pp23–28). Forms T24–T26 cover energy sales projections, revenue from tariffs and charges, and demand in MVA (pp29–34). Forms T27–T32 deal with working capital, non-tariff income, grants/subsidies, and existing/proposed tariff schedules with revenue projections (pp35–40). Forms T33–T36 report transmission losses and voltage-wise monthly losses (pp41–44). Forms T37–T40 cover metering status, voltage profile, outages and transformer failures (pp45–49). Forms T41–T45 cover peak and off-peak demand, income tax provisions, and transmission availability (pp50–54).

Across the forms, the filing utility generally must supply previous-year actuals, current-year estimates and projections for three control-period years, often separating transmission business from SLDC business (e.g. pp2–3, p36). The capital expenditure format names FY 2020-21, FY 2021-22 and FY 2022-23 as the second control period (pp16–17); the O&M normative format uses FY 2017-18 to FY 2019-20 for a three-year average (p5). The document is procedural: it specifies what data to file, not the allowed tariff values.

Primary topics
ARR and true-up, Transmission tariff, SLDC and RLDC fees and charges

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document