Terms and Conditions for Determination of Generation, Transmission, Wheeling and Retail Supply Tariff (MYT Regulations 2019) — 1st Amendment, 2019
"Punjab State Electricity Regulatory Commission (Terms and Conditions for Determination of Generation, Transmission, Wheeling and Retail Supply Tariff)" (PSERC MYT Regulations 2019) (1st Amendment) Regulations, 2019
AmendmentDated 16 Mar 2022Published in the Gazette 18 Mar 2022No. PSERC/Secy/Regu/163.- dated The16th March, 2022
Replaced by Generation, Transmission, Wheeling and Retail Supply Tariff (MYT) Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software. Check the regulator's original before you rely on it.
A two-page PSERC notification dated 16 March 2022, published in the Punjab Gazette on 18 March 2022, making the first amendment to the Commission's MYT Regulations 2019 — the framework governing determination of generation, transmission, wheeling and retail supply tariffs (p1). It comes into force on Gazette publication (p1).
The amendment is narrow and entirely about interest on working capital. It inserts additional provisos into Regulation 33.1 (p1–2), Regulations 43.1 and 43.2 (p2), and Regulation 51.1 (p2). The provisos specify how working capital is to be treated at truing-up: for a generating station, computation is based on the lower of annual plant load factor or normative availability (p1); for any year, the working capital requirement is re-computed on trued-up receivables, O&M expenses and other working-capital components as approved by the Commission at truing-up (p1–2); and the gap between normative and actual (documented) interest is classified as 'excess normative' or 'deficit normative' (p1–2).
The treatment direction is asymmetrical: 'excess normative' is passed on to consumers over a period the Commission specifies in its order, while 'deficit normative' is borne by the applicant (p2). Nothing else in the principal regulations is touched.
Read with this
The regulation
Procedures and orders made under it
- Date not statedFormats - Distribution (Form D1–D34)
- Date not statedTransmission and SLDC ARR and Tariff Petition Formats
- Date not statedGeneration Formats (Forms G1–G33(B))
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.