DSM Regulations, 2025 — Clarification Order on SLDC Energy Accounting Procedure

Clarification on issues raised by SLDC along with Submission of Detailed Accounting Procedure under Clauses 11(i) and 15(vi) of the BERC (Deviation Settlement Mechanism and Related Matters) Regulations, 2025

OrderDated 22 Sep 2026

Made under the Deviation Settlement Mechanism and Related Matters Regulations, 2025.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on berc.co.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a three-page clarification order by the Bihar Electricity Regulatory Commission responding to points raised by the State Load Despatch Centre (SLDC) in connection with the Detailed Energy Accounting Procedure that SLDC is required to frame under Clauses 11(i) and 15(vi) of the BERC (Deviation Settlement Mechanism and Related Matters) Regulations, 2025. The background (p1) records the notification of those Regulations on 12.02.2026, SLDC's stakeholder circulation of the draft procedure (Letter No. 132 dated 10.03.2026, comments by 17.03.2026), and SLDC's subsequent submission and clarification request (letter no. 273 dated 20.05.2026).

The Commission then disposes of three points (pp1–3). On bagasse/biomass sugar mills, it accepts SLDC's proposal and clarifies that the deviation charges under Regulation 9(C) of the 2025 Regulations apply to bagasse- and biomass-based renewable energy plants (p2). On partial open access consumers, it reads the Regulation 3 definition of 'Buyer' — reproduced in the order — as covering only InSTS-connected full open access consumers, and says partial open access consumers fall outside it (p2). On NTPC Barauni's suggestion, it clarifies that the State Deviation Pool Account under Regulation 10(e) shall be charged for payment to the seller for over-injection and to the buyer for under-drawal, as applicable (p3).

On the two points where stakeholders wanted alignment with the CERC DSM framework, the Commission declines to amend the Regulations and instead invites SLDC to file a separate petition if it wishes to pursue a change (pp2–3). The matter is disposed of with the clarifications (p3).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement, Open access

Read with this

Voltaic last read BERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document BERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on berc.co.in ↗

Report an issue with this document