Electricity Supply Code and Connected Matters Regulations, 2004 — Fifth Amendment Regulations, 2006

The Rajasthan Electricity Regulatory Commission (Electricity Supply Code and Connected Matters) (Fifth Amendment) Regulations, 2006.

AmendmentDated 2 Sep 2006No. RERC/Secy/Reg.54 dated 2 .9. 2006

Replaced by Electricity Supply Code and Connected Matters Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

Amends a regulation Voltaic does not hold.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Rajasthan Electricity Regulatory Commission's Fifth Amendment to the Electricity Supply Code and Connected Matters Regulations, 2004, issued as No. RERC/Secy/Reg.54 and dated 2.9.2006 (p1). It is the vehicle for folding the State Government's Revised Agriculture Policy into the Supply Code, following directives of 18.9.2004 and later amendments up to 23.1.2006 (p1, p11). The regulation itself is to come into force from publication in the official gazette, though the gazette date is not printed (p1).

Clause 2 rewrites the agriculture-connection provisions of the 2004 Code. Amendments 1–2 add application-money, demand-note, connected-load and L-form requirements to Clauses 6[2] and 6[7] (pp1–2). Amendment 3 replaces Clause 6A with technical feasibility and works-estimate rules for agricultural connections—transformer loading, direct feeder, LT-line length, pole provision and metering (p2). Amendment 4 adds priority rules for general, special, farm-house and co-operative/lift-irrigation categories, including subdivision-wise priority and re-determination after demand-note payment (pp2–4). Amendment 5 replaces the old unmetered-supply cut-off in Clause 25[1] with conversion to metered supply within a period notified by the Commission under s.55(1) (p4). Amendment 6 replaces Clause 40 restoration-of-supply periods and charges, with separate treatment for agriculture, industrial and other consumers (pp4–5). Amendment 7 inserts Clause 40(A) to convert special, nursery, farm-house and Hara Chara connections to general category, including a retrospective conversion date of 19.11.2005 for older connections (pp5–6). Amendment 8 inserts theft provisions for agriculture in Clause 41(A) (p6). Amendment 9 inserts Clause 43(3) on inspection, excess load, load extension and second connections (pp7–8). Amendments 10–12 replace schedule entries for application fees, amounts deposited with applications and additional amounts for agricultural connections (pp8–9).

The amendments are retrospective: they take effect from 18.9.2004, except specified clauses with dates ranging from 2.12.2004 to 16.12.2005 (p10). An explanatory note at p11 records the Advocate General's advice and the policy paragraphs left out of the amendment.

Standard name
Electricity Supply Code
Primary topics
Agricultural supply, New connections and load changes, Connection and miscellaneous charges

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document