Electricity Supply Code and Connected Matters, 2004 — Eighth Amendment, 2007

The Rajasthan Electricity Regulatory Commission (Electricity Supply Code and Connected Matters - Eighth Amendment) Regulations, 2004

AmendmentDated 15 Oct 2007No. RERC/Secy/Reg.71 dated 15th October, 2007

Replaced by Electricity Supply Code and Connected Matters Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

Amends a regulation Voltaic does not hold.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Eighth Amendment to the RERC (Electricity Supply Code and Connected Matters) Regulations, 2004, notified by the Rajasthan Electricity Regulatory Commission on 15 October 2007 under sections 43 to 48, 50, 55 and 56 read with section 181 of the Electricity Act 2003 (p1). It takes effect from publication in the official gazette; the gazette date is not printed (p1). Unusually, it does not merely list changes: for each amended clause it sets out the full amended wording, so it reads as a working version of the supply code's consumer-facing provisions.

Pages 1–3 deal with the connection process. They cover how security is taken from LT versus HT applicants (cl 6(3)); how incomplete applications are handled, with a defect notice, cancellation, forfeiture of the application fee and refund with bank-rate interest (cl 6(6)); a category- and locality-wise priority register with first-come-first-serve release of connections (cl 12); refunds when an applicant withdraws or refuses supply (cl 13); recovery of minimum charges from applicants who delay taking supply (cl 14); security for large industrial consumers on special fortnightly billing (cl 16(1)); review of security against actual first-year consumption (cl 16(2)(a)); and refund of excess security and interest on deposits (cll 19–21). A replaced clause 6(A) routes agriculture consumer matters — application, priority, load increase, shifting, restoration — to State Government policy directions under section 108, while barring the licensee from revising application fee, line cost or rental charges except through Commission regulations (p2).

Pages 4–7 cover metering, dues and enforcement: assessment for temporary connections (cl 29(1)(iv)); testing of defective meters at Commission-designated laboratories (cl 30(1)) and the timetable for intimating assessment and adjusting it in later bills (cl 30(2)); a two-year limitation on recovery of old dues (cl 39(1)); a time-limited scheme for waiver or reduction of interest/LPS/DPS (cl 39(3)); restoration of supply procedure (cl 40); and a rewritten theft/unauthorized-use regime under cl 41(A) — period of assessment, assessment at twice the applicable tariff, the provisional assessment order and notice, the deposit precondition for appeal, who may disconnect, complaints to the Special Court or police, compounding, restoration within 48 hours and debarment on repeat conviction (pp4–7).

Page 8 deletes a set of clauses, notes and provisos from the principal regulations and revises the Schedule's application deposits and LT extension charges; page 9 gives the standard line-cost schedule for HT/EHV lines and substation bays and renames 'minimum charges'/'minimum billing' as 'fixed charges' following the Commission's 31 August 2007 retail tariff rationalisation order (pp8–9).

Standard name
Electricity Supply Code
Primary topics
New connections and load changes, Security deposit, Theft and unauthorised use

Read with this

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document