Renewable Purchase Obligation and its Compliance Regulations, 2025 — Third Amendment

APSERC (Renewable Purchase Obligation and its compliance) Regulations, 2025 (Third Amendment).

AmendmentDated 10 Sep 2025Published in the Gazette 15 Sep 2025APSERC/NOTIFICATION/52/2025 dated The 10th September, 2025

Amends the Renewable Power Purchase Obligation and its Compliance Regulations, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on apserc.nic.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the third amendment to APSERC's Renewable Power Purchase Obligation and its Compliance Regulations, 2012. It was issued on 10 September 2025 and published in the Arunachal Pradesh Gazette on 15 September 2025, the date it comes into force (p1).

The operative change replaces the RPO trajectory in Regulation 4 of the Principal Regulation with a year-wise table running from FY 2024-25 to FY 2029-30, split into wind, hydro, distributed, other and total renewable energy components (p1). The preamble anchors this to the Ministry of Power's S.O. 4617(E) of 20 October 2023 on minimum non-fossil consumption shares for designated consumers (p1).

The notes to the table do most of the substantive work (p2). Note 1 halves Arunachal Pradesh's distributed renewable energy component and folds the remainder into the 'other' bucket. Notes 2–5 define which projects count against each component: wind and hydro only from projects commissioned after 31 March 2024 (hydro may be met from free power to the State/DISCOM); distributed only from projects under 10 MW across all solar configurations, with a daily capacity-to-energy multiplier where generation data is missing; and 'other' from pre-1 April 2024 projects. Clauses 3–5 allow shortfalls in wind or hydro to be swapped with each other or with the other component. Clause 6 requires open access and captive consumers to meet the total target irrespective of source; clause 7 permits compliance through RECs under the CERC 2022 framework; clause 8 treats shortfall as non-compliance penalised under the Energy Conservation Act; clause 9 extends APEDA's role to RPO monitoring with quarterly reports to the Commission; clauses 10–11 cover BEE data reporting and the validity of the trajectory (p2).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Renewable energy certificates (REC)

Read with this

Voltaic last read APSERC's website for final documents on 30 Sep 2026 and for drafts on 23 Nov 2026 (2 pages). A document APSERC issued after the page that lists it was read may not be held by Voltaic yet.