Maharashtra Electricity Regulatory Commission (Multi Year Tariff) Regulations, 2024
Draft regulationReleased with the notice dated 7 Mar 2024
Draft
A proposal that has since been finalised as the Multi Year Tariff Regulations, 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the draft of the tariff rulebook the Maharashtra Electricity Regulatory Commission proposes to apply to every regulated electricity business in the State for the five years from 1 April 2025 to 31 March 2030 (p6). It would replace the 2019 MYT Regulations outright, while leaving the older Regulations in charge of ARR, tariff and review matters for periods up to 31 March 2025 (p6–7). It covers generating companies (including those drawing coal or lignite from an integrated mine), transmission licensees, distribution and deemed distribution licensees, the MSLDC and the STU (p6).
Framework and procedure. Part A sets the multi-year architecture — forecast ARR and revenue for each year of the control period, true-up for the first four years and provisional true-up for the fifth, and a split between controllable and uncontrollable factors, with one-third/two-thirds sharing of gains and losses and a monthly fuel adjustment charge (ZFAC) plus an annual 'other uncontrollable cost' pass-through (p28–38). Part B lays down the filing, admission, public-notice (two English and two Marathi dailies) and 120-day tariff-order procedure, and allows generators and transmission licensees to charge below the ceiling tariff by agreement (p39–45). Part C routes distribution licensees' procurement through the Resource Adequacy Regulations, 2024, Section 63 bidding, prior approval of long-term and medium-term PPAs, and a defined window for additional procurement (p46–50).
Financial principles. Part D is the accounting engine: prudence check on revenue, revenue expenditure and capex; capital cost and additional capitalisation; consumer contributions and grants; the debt:equity split; depreciation under two schedules; a base return on equity topped up by performance-linked return tied to ramp rate, mean time between failures, peak-hour availability and transmission/wires availability; interest on loan and working capital; forex variation; income tax; contingency reserves; rebates; and delayed payment charges (p51–87).
Business-specific parts. Part E governs generation tariffs — components, fuel utilisation plan, renovation and modernisation, a 'special allowance' option for plants past useful life, O&M norms and detailed thermal and hydro operating norms, capacity and energy charge computation, declared-capacity demonstration and deviation (p88–125). Part F builds a separate cost-plus methodology for the input price of coal or lignite from integrated mines, running from run-of-mine cost through overburden, GCV and non-tariff-income adjustments to credit notes (p126–139). Part G pools transmission ARRs into a total system cost and allocates it through Base Transmission Capacity Rights, with O&M norms fixed licensee by licensee (p140–160). Part H requires wires and retail supply accounts to be separated and gives a fallback allocation matrix, then sets wheeling charges and losses (p161–171). Part I covers retail supply: ARR components, sales forecast, O&M and demand-side measures, cross-subsidy and additional surcharge, distribution losses, tariff and fixed-charge determination, the 'ceiling tariff' regime for parallel licensees, and time-of-day tariffs (p172–186). Part J and Part K set fees and charges for the MSLDC and the STU, including development funds and KPI-linked incentives (p187–204). Part L creates tariff frameworks for standalone battery storage and pumped storage hydro (p205–220). Part M handles State subsidy pass-through and Part N the usual practice-direction, relax, amend and remove-difficulties powers (p221–222). Seven annexures carry the depreciation schedules, the distribution asset-allocation methodology, the competitive-bidding threshold, the life-cycle-cost format and the transmission availability computation (p223–243).
Read with this
The regulation
- Date not statedMulti Year Tariff Regulations, 2024
Commencement notices and reasons
- Dated 19 Aug 2024Multi Year Tariff Regulations, 2024 — Statement of Reasons
Other copies of these documents (1)
- Date not statedMulti Year Tariff Regulations, 2024
Earlier drafts
- Dated 7 Mar 2024Public notice: Public Notice Inviting Comments, Suggestions and Objections on Draft Regulations, March 2024
- Released with the notice dated 7 Mar 2024Explanatory memorandum: Explanatory Memorandum on Draft Multi Year Tariff Regulations, 2024
- Dated 28 Mar 2024Notice extending the date for comments: Public Notice — Extension of Time for Filing Comments on Draft Regulations
3 more documents belong here and are not on Voltaic: 1 copy in another language, 1 draft or notice on a draft not held as English text and 1 procedure or order made under it.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.