Summary written by software, from pages 1 to 40 of 54. Check the regulator's original before you rely on it.
Regulation No. 03 of 2026 is the Telangana Electricity Regulatory Commission's principal framework for resource adequacy (p1). It applies across Telangana and comes into force on Gazette publication (p1). Its objective is to plan generation, transmission and distribution resources to meet projected demand reliably with an optimum generation mix (p2). The framework covers demand assessment and forecasting, generation resource planning, transmission and distribution network planning, procurement planning, and monitoring and compliance, on a 10-year annual rolling basis (p5). DISCOMs must prepare Long-, Medium- and Short-Term Distribution Resource Adequacy Plans (LT/MT/ST-DRAP), while the STU prepares transmission planning criteria and files the state resource adequacy plan with MYT or annual tariff petitions (p5, p15).
Chapter 3 sets out demand forecasting duties (p5-9): DISCOMs forecast hourly or sub-hourly demand and energy by consumer category using CEA guidelines and specified statistical and modelling methods; they develop scenarios and adjust for DSM, open access, distributed energy resources, EVs, tariff signals, agricultural load and policy drivers (p6-8). SLDC aggregates state forecasts and submits them to CEA, NLDC and RLDC by 31 May each year (p9).
Chapter 4 governs generation resource planning (p9-16): DISCOMs map existing, upcoming and retiring resources; compute capacity credit for contracted resources; apply the net-load method for solar and wind capacity credit; use CEA or Commission factors for storage, hydro and thermal; determine planning reserve margin through reliability indices; and calculate resource adequacy requirement and gaps against national and state resource adequacy plans (p10-15).
Chapter 5 covers procurement planning (p16-19): optimal resource mix, least-cost modelling, contracting with long-, medium- and short-term resources, renewable and storage procurement under Ministry of Power competitive bidding guidelines, use of DEEP, PUSHP, Term-Ahead Markets and OTC platform, prior Commission approval for PPAs and PSAs, and reporting of emergency procurement (p16-19).
Chapter 6 makes compliance mandatory, with Commission-determined non-compliance charges (p19). Chapter 7 sets out data-sharing and annual timelines for DISCOMs, SLDC and STU, including submission of LT-DRAP to the Commission and approval (p19-23). Chapter 8 requires website disclosure of procurement and merit-order data, creation of dedicated planning and real-time procurement cells, consultation in resource adequacy plan preparation, and preserves Commission powers to issue directions, relax provisions, remove difficulties and amend (p23-25).
Annexure-I provides modelling methodology and constraints (p26-29); Annexure-II lists formats 1-14 (p29), with Formats 1-3 visible by p40 covering demand forecast, monthly ex-bus energy requirement, and 10-year power supply projections (p31-40); Annexure-III gives the firm-capacity and resource adequacy requirement formula (p30).
Read with this
The regulation
- Dated 24 Feb 2026Framework for Resource Adequacy Regulation, 2026
Procedures and orders made under it
Earlier drafts
- Dated 15 Nov 2025Framework for Resource Adequacy Regulations, 2025 — Draft
- Released with the draft dated 15 Nov 2025Public notice: Draft Framework for Resource Adequacy Regulations, 2025 — Public Notice
- Released with the draft dated 15 Nov 2025Annexure or form: Telangana Framework for Resource Adequacy Regulations, 2025 — Annexure-II (Formats 1 to 14) — Draft
Voltaic last read TSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document TSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.