EXPLANATORY MEMORANDUM - DRAFT DELHI ELECTRICITY REGULATORY COMMISSION (TERMS AND CONDITIONS FOR GREEN ENERGY OPEN ACCESS)(FIRST AMENDMENT) REGULATIONS, 2026.

Explanatory memorandum to a draftReleased with the notice dated 15 Apr 2026

Explanatory memorandum to the Green Energy Open Access (First Amendment) Regulations, 2026 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Commission's explanatory memorandum for a draft first amendment to the Delhi Electricity Regulatory Commission (Terms and Conditions for Green Energy Open Access) Regulations, 2024, the "Principal Regulations" notified on 12 November 2024 (p1). It is a reasons document, not the amendment itself: it sets out why the Commission proposes to change the eligibility rule and what the change is meant to achieve.

The background paragraphs (p1) record that the Principal Regulations, framed in pursuance of the Ministry of Power's Electricity (Promoting Renewable Energy through Green Energy Open Access) Rules, 2022, limited Green Energy Open Access to consumers connected at 11 kV and above who also had a contracted demand or sanctioned load of 100 kW and above. The Commission's concern is that the voltage limb excluded consumers who satisfy the load criterion but are connected below 11 kV, producing differential treatment of consumers with identical load characteristics.

Paragraphs (4)–(7) (p1–2) give the triggers and reasoning: implementation experience, especially in telecom and commercial infrastructure with dispersed, predominantly LT loads; discussions at Government of NCT of Delhi / Department of Power meetings; comparator frameworks in Gujarat and Maharashtra that have operationalised Green Energy Open Access closer to the national framework; and the pending Draft Central Electricity Authority (Installation and Operation of Meters) (5th Amendment) Regulations, 2025, which the Commission notes is still to be notified while States have proceeded anyway. The Commission concludes that the voltage restriction is not warranted and not consistent with wider access.

Paragraphs (8)–(11) (p2) state the scope and effect: the amendment is confined to deleting the words "connected at 11 kV and above" from the relevant provisions, and adopts a uniform load-based criterion. The Commission stresses the change is purely enabling and prospective, leaving existing approvals, charges, surcharges, banking arrangements, metering responsibility, scheduling provisions, and technical feasibility and system availability requirements untouched. Expected outcomes are wider access below 11 kV and greater participation by telecom, MSME and commercial consumers.

Standard name
Green Energy Open Access Regulations
Primary topics
Green energy open access

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.