Group Net Metering and Virtual Net Metering for Renewable Energy (Fifth Amendment) Guidelines, 2024

Delhi Electricity Regulatory Commission (Group Net Metering and Virtual Net Metering for Renewable Energy) (Fifth Amendment) Guidelines, 2024

AmendmentDated 15 Mar 2024In force from 1 Apr 2024F.3(620)/Tariff-Engg./DERC/2020-21/6846 dated 15/03/2024

Amends the Group Net Metering and Virtual Net Metering for Renewable Energy Guidelines, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the fifth amendment to DERC's 2019 Group Net Metering and Virtual Net Metering Guidelines, notified on 15 March 2024 and in force from 1 April 2024 until further amendment (p1). It substitutes four provisions of the principal guidelines.

On definitions (p1), it rewrites Guideline 2 so that both GNM and VNM expressly cover a Battery Energy Storage System charged through a renewable energy system, and so that systems may sit at single or multiple locations. GNM covers surplus energy exported through a net meter and adjusted across more than one service connection of the same consumer; VNM covers the entire generation exported through a renewable energy/gross meter and shared among participating consumers — both within the same distribution licensee's area of supply.

Guideline 3(6) (p1–2) shifts capital expenditure for service line cum development (SLD) and network augmentation onto distribution licensees, recovered through ARR. The SLD waiver is confined to 11 kV and below networks and capped at cumulative capacity per licensee — BRPL 75 MW, TPDDL 50 MW, BYPL 30 MW, NDMC 10 MW. Licensees must submit quarterly progress reports on net metering, GNM and VNM to the Commission and EE&RM, DoP, GNCTD.

Guideline 3(8) (p2) limits ground-mounted RE systems to five times the sanctioned load of participating consumers, with an absolute ceiling of 10 MW, and states there is no capping on rooftop solar under either framework.

Guideline 13 (p2) is the commercial core: RE systems commissioned up to 31 March 2027 get 100% exemption from wheeling charge, banking charge, cross subsidy surcharge and other charges for useful life. Projects commissioned up to 31 March 2030 start at 25% of those charges and rise in 25% steps every third year to 100%. Licensees must display available VNM/GNM capacity on their websites, updated quarterly.

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Open access charges, Energy storage deployment

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.