Group Net Metering and Virtual Net Metering for Renewable Energy (Seventh Amendment) Guidelines, 2025 — Draft

Delhi Electricity Regulatory Commission (Group Net Metering and Virtual Net Metering for Renewable Energy) (Seventh Amendment) Guidelines, 2025

Draft amendmentDated 17 Dec 2025F.3(620)/Tariff-Engg./DERC/2020-21/6846 dated 17/12/2025

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft amendment issued by the Delhi Electricity Regulatory Commission on 17 December 2025, the seventh to the DERC (Group Net Metering and Virtual Net Metering for Renewable Energy) Guidelines, 2019 (p1). It is a short instrument — five clauses over two pages — each of which substitutes a provision of the Principal Guidelines.

Clause 1 gives the title and provides that the amendment takes effect from the date it is uploaded on the DERC website and stays in force until further amendment; no uploading date is printed (p1). Clause 2 rewrites the applicability clause so that the Virtual Net Metering framework covers all consumers of NCT of Delhi, expressly including consumers on a single point of supply (p1). Clause 3 replaces the clause governing a consumer's option to change its share of credit or to add participating service connections, permitting this twice in a financial year with two months' advance notice under the existing agreement/MoU (p1). Clause 4 changes the time block referred to in the credit clause from 'off peak' to 'normal' (p1).

Clause 5 carries the commercial substance for licensees: distribution licensees must facilitate and bear capital expenditure on service line cum development and network augmentation for renewable energy projects and pass it through in ARR, with the waiver confined to 11 kV and below network and capped cumulatively at 110 MW, 100 MW, 30 MW and 10 MW for BRPL, TPDDL, BYPL and NDMC respectively; licensees must also submit quarterly progress reports on NM, GNM and VNM to the Commission and EE&RM, DoP, GoNCTD (p2).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Connection and miscellaneous charges

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on derc.gov.in ↗

Report an issue with this document