CERC · Central Electricity Regulatory Commission

Deviation Settlement Mechanism and Related Matters Regulations, 2022

Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2022

RegulationDated 14 Mar 2022No. L-1/260/2021/CERC dated 14

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken, including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations, shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2022 replace the 2014 DSM framework with a mechanism for pricing and settling deviations from schedule by grid users. They are made under s.178 read with s.79(1)(c) and (h) of the Electricity Act, 2003; the notification is dated 14 March 2022, but commencement is deferred to a date the Commission notifies separately (p1).

Regulations 1–4 give the short title, the objective — a commercial mechanism so that grid users do not deviate from schedule, in the interest of grid security and stability — the definitions, and the scope, which covers all grid-connected regional entities and other entities engaged in inter-State purchase and sale of electricity (p3–4). The definitions draw the distinctions the charging scheme runs on: general sellers versus WS sellers (wind, solar or wind-solar hybrid), Contract rate, Reference Charge Rate, Available Capacity for WS sellers, and RE-rich States (p1–3).

Regulations 5–8 are the operative core. Regulation 5 obliges every regional entity to adhere to schedule, with deviations managed by the Load Despatch Centre under the Ancillary Services Regulations. Regulation 6 sets separate deviation formulas in MWh and in per cent for general sellers, WS sellers (denominated on Available Capacity) and buyers. Regulation 7 fixes the normal rate of deviation charges, ordinarily the weighted average ancillary service charge across regions, with a transitional proviso for one year from effect using the highest of Day Ahead ACP, Real Time Market ACP and the weighted average ancillary service charge (p4–5). Regulation 8 sets the slab structure of charges payable to and from the pool account, treating under-injection and over-injection by sellers and under-drawal and over-drawal by buyers, with distinct slabs for buyers generally, buyers in RE-rich States and WS sellers, and special treatment for infirm power and start-up/auxiliary drawal (p5–8).

Regulations 9–10 put the accounting machinery in place: weekly RLDC data to the RPC secretariat, statements of charges issued to regional entities, a regional Deviation and Ancillary Service Pool Account that receives deviation charges, ancillary service payments and other notified amounts and funds SRAS-Up and TRAS-Up costs, with inter-region deficit sharing and residual recovery through RLDC fees and charges; payment within seven days, a late payment surcharge, and a Letter of Credit requirement for entities that defaulted in the previous financial year (p8–10).

Regulations 11–13 give the Commission power to relax provisions and to issue practice directions to remove difficulty, and repeal the 2014 regulations with savings and a rename of the Regional Deviation Pool Account Fund (p10–11).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Ancillary services and reserves, Energy accounting and settlement

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document