CERC · Central Electricity Regulatory Commission
Deviation Settlement Mechanism and Related Matters Regulations, 2022 — grid-security directions, 26 December 2022
Directions in the interest of grid security, in pursuance of the provisions of the Electricity Act, 2003 and the provisions of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2022
OrderDated 26 Dec 2022In force from 28 Dec 2022Petition No. 16/SM/2022 dated 26th December, 2022
Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2024
See that regulation for the date it took effect and for anything it keeps in force.
Made under the Deviation Settlement Mechanism and Related Matters Regulations, 2022.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken, including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations, shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
CERC's suo-motu order of 26 December 2022 (Petition No. 16/SM/2022) is an emergency grid-security intervention issued barely two weeks after the DSM Regulations, 2022 took effect on 5 December 2022 (p1). The Commission had monitored implementation, held discussions with Grid-India on 20 and 23 December and with regional generating stations on 23 December, and reviewed frequency data (p1–2).
Pages 1–3 set out the diagnosis: frequency excursions fell, but time spent outside the operating band rose by roughly 20%; Grid-India reported primary response below pre-DSM levels, thin SRAS and RRAS reserves, and RLNG gas generation pressed into ancillary service. The Commission read this as a tendency to over-schedule — over-injection by generators coinciding with under-drawal by discoms — producing sustained high frequency (p3–4).
Invoking Regulation 12 of the DSM Regulations (power to remove difficulty, quoted at p4) and s.79(1)(c) of the Act, the order issues two directions. First, it caps the normal rate of deviation charge under Regulation 7 at Rs 12 per kWh until further orders, because ancillary-service-driven rates near Rs 40/kWh were seen to create perverse incentives to under-draw or over-inject (p4–5). Second, it displaces Regulation 8(1) and (2) with frequency-contingent treatment: at 50.05 Hz or above, over-injection and under-drawal draw zero payment and under-injection is paid back at 50% of the reference charge rate; at 49.90 Hz or below, over-injection is paid at 150% of the reference charge rate — run-of-river and municipal-solid-waste stations being carved out (p5–6).
The directions take effect from 00:00 hours of 28 December 2022 and hold until further orders; the Commission calls them an interim exigency measure and promises separate amendments to the DSM Regulations later. Grid-India must report weekly on who caused frequency deviations, on primary-response and AGC performance, on reasons for shortfalls and on reserve procurement and deployment, and must give the order wide publicity (p6).
Read with this
The regulation
- Dated 14 Mar 2022Deviation Settlement Mechanism and Related Matters Regulations, 2022
Commencement notices and reasons
Procedures and orders made under it
Other copies of these documents (1)
- Dated 14 Mar 2022Deviation Settlement Mechanism and Related Matters Regulations, 2022
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.