Skip to content

CERC · Central Electricity Regulatory Commission

Notification, effective date 05.12.2022

Commencement noticeDated 31 Oct 2022No. L-1/260/2021/CERC dated 31st October 2022

Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2024

See that regulation for the date it took effect and for anything it keeps in force.

Commencement notice for the Deviation Settlement Mechanism and Related Matters Regulations, 2022. The dates are in the notice.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken, including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations, shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A one-page CERC notification (p1) that fixes the date on which the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2022 take effect. It records that those Regulations were published in Part-III, Section 4, No. 147 of the Gazette of India Extraordinary on 22.03.2022, and that Regulation 1(2) left commencement to a date to be notified separately by the Commission (p1). It then notifies that the Regulations shall come into force with effect from 05.12.2022 (p1).

The substantive DSM Regulations are not reproduced here — this document supplies only the commencement date. It is signed by the Secretary on 31.10.2022, roughly five weeks before the date it sets (p1). For anything other than the effective date, an analyst must go to the 2022 Regulations themselves.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM)

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document