APERC · Andhra Pradesh Electricity Regulatory Commission

Licensees' Standards of Performance Regulation, 2004 — Second Amendment, 2013

Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Second Amendment Regulation, 2013.

AmendmentDated 7 Aug 2013Published in the Gazette 8 Aug 2013Regulation No.9 of 2013

Amends the Licensees' Standards of Performance Regulation, 2004.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on aperc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to the Andhra Pradesh Electricity Regulatory Commission (Licensees' Standards of Performance) Regulation, 2004, issued as Regulation No. 9 of 2013 and published in the A.P. Gazette Extraordinary of 8 August 2013 (p1). The recitals set out the trigger: consumer associations and activists argued at public hearings on DISCOM ARR and FSA filings that the compensation fixed in 2004 had lost its deterrent value, so the Commission issued a draft, took comments and held a public hearing on 5 June 2013 (p1).

The operative text is short. Clause 1 gives the short title and ties commencement to Gazette publication (pp1-2). Clause 2 inserts a fourth provision into clause 5 of the principal regulation: a distribution licensee — expressly including deemed licensees and exemptees — that fails to comply with the Overall Standards of Performance in Schedule-III, or fails to provide service supporting such compliance, is treated as contravening the Act, rules, regulations or Commission directions, and may be penalised after a hearing; penalty receipts may be used by the Commission for Consumer Advocacy (p2).

Clause 3 substitutes Schedule-II in full (pp2-5). The replacement schedule sets, service item by service item, a time standard and the compensation payable on breach, differentiated between cities/towns and rural areas and between events affecting a single consumer and several. It covers fuse-off calls, overhead and underground cable breakdowns, distribution transformer failure, scheduled outages, voltage fluctuation (with separate timelines where network enhancement or a new substation is needed), meter complaints including burnt meters, processing of new-connection and additional-load applications by voltage level, release of supply after payment of charges, title transfer and category/LT-HT conversion, billing complaints, reconnection after disconnection and wrongful disconnection or wrongful reconnection charges (pp2-4).

The same enclosure carries the manner of payment: every complaint must be registered and given a unique complaint identification number; the SMS advising rectification fixes the time of compliance; consumer-wise records must be kept; claims go within 30 days to a designated headquarters officer who also monitors compliance; compensation is paid by adjustment against bills within 90 days; and unaddressed claims escalate to the CGRF and then the Vidyuth Ombudsman (p5).

Standard name
Standards of Performance
Primary topics
Standards of performance, New connections and load changes, Metering

Read with this

Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.