KSERC · Kerala State Electricity Regulatory Commission
Renewable Energy and Net Metering Regulations, 2020 — First Amendment, 2022
Kerala State Electricity Regulatory Commission (Renewable Energy and Net Metering) (First Amendment) Regulations, 2022
AmendmentDated 15 Jul 2022In force from 1 Aug 2022No. 1204/D(T)/2019/KSERC dated 15.07.2022
Replaced by Renewable Energy and Related Matters Regulations, 2025
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Renewable Energy and Net Metering Regulations, 2020.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken under the above Regulations shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the first amendment to the KSERC (Renewable Energy and Net Metering) Regulations, 2020, issued by notification dated 15.07.2022 and brought into force from 01.08.2022 (p1). It rewrites thirty provisions of the 2020 parent regulation, adds new definitions and new regulations, revises the RPO trajectory, and replaces the generic-tariff annexures for the remainder of the control period ending 31.03.2024 (p1, p18).
The opening clauses fix who the 2020 regulations apply to. Regulation 1(2) is rewritten, with provisos preserving pre-2003 captive generators under their existing agreements, allowing bills issued from 5 June 2020 to the date of effect to stand unrevised, and deferring any introduction of gross metering until licensees fully comply with their RPO (p1–2). The Explanatory Note (p2) says the original 'existing and new' wording was an inadvertent error: entities governed by the 2015 RE Regulations and the 2014 Grid Interactive Distributed Solar Energy Systems Regulations continue under those, though the 2020 facilities such as banking on payment of charges are available to them. New definitions are inserted for Average Power Purchase Cost, Gross-Metering, Hydro Power Obligation (large hydro above 25 MW commissioned on or after 08.03.2019) and Ocean Energy, and the Settlement Period definition is rewritten (p2–3).
The RPO table in Regulation 3 is revised to add targets for FY 2022-23 and 2023-24 and an HPO column (p4). Net-metering eligibility is broadened and narrowed at once: prosumers may install RE capacity above their connected load or contract demand but lose net metering and are treated like prosumers above 1 MW; residential flats on LT domestic tariff for common services may net-meter up to 100 kW (p4). A new Regulation 17A obliges the distribution licensee to run an online application portal, publish a standardised rooftop procedure, a single point of contact, charges, empanelled service providers and incentive information (p4–5). Regulation 18 gains provisos on hard-copy and online applications, a deemed-receipt date, a tracking mechanism, a new 18A requiring the licensee to upgrade distribution infrastructure for connectivity, and a new 20A on passing through Central/State financial incentives (p5–6).
On tariffs, 'commissioned' in Regulation 31 becomes 'declared date of commercial operation' (p6–7); Regulation 35 is revised so project-specific tariffs apply above 1 MW while generic tariffs may be determined for solar up to 1 MW, wind up to 5 MW and small hydro up to 2 MW, as a ceiling, with the purchaser paying the lower of generic or project-specific tariff, and competitive bidding under s.63 preserved (p7–8). New Regulation 35(4A) anchors the normative parameters and generic tariffs for these categories in Annexures IV, V and VI (p8). Regulation 38 gives must-run status to RE plants with approved PPAs; Regulation 52(3) restates O&M escalation; Regulation 54 capital cost and CUF provisions are split so the 19% CUF applies up to 31.07.2022 and 21% from 01.08.2022 (p9–10). A new Regulation 56(A) allows the Commission to permit gross metering for prosumers who wish to sell all generation (p11). Generation-based incentives for off-grid captive solar are extended from 30.09.2021 to the end of the control period, and the daily penalty on the distribution licensee for missed timelines is halved to Rs 500 per day (p11). Regulation 68's annexure list is replaced (p11–12).
Annexures IV, V and VI(1)-(3) (p13–17) give the normative parameters and computed generic tariffs for small hydro below 2 MW, wind below 5 MW and three solar PV size bands, all for 01.08.2022 to 31.03.2024. The closing Explanatory Note (p18) records the pre-publication and hearing history and ties the amendment to s.86(1)(e) of the Act and the Electricity (Rights of Consumers) Rules, 2020.
Read with this
The regulation
- Dated 7 Feb 2020Renewable Energy and Net Metering Regulations, 2020
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (2)
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.