Skip to content

KSERC · Kerala State Electricity Regulatory Commission

Renewable Energy and Net Metering Regulations, 2020 — First Amendment, 2022

Kerala State Electricity Regulatory Commission (Renewable Energy and Net Metering) (First Amendment) Regulations, 2022

Amendment · Gazette copyDated 15 Jul 2022Published in the Gazette 18 Jul 2022In force from 1 Aug 2022No. 1204/D(T)/2019/KSERC dated 15th July, 2022

Replaced by Renewable Energy and Related Matters Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the Renewable Energy and Net Metering Regulations, 2020 — First Amendment, 2022.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken under the above Regulations shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on dev.erckerala.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Kerala State Electricity Regulatory Commission's first amendment to its Renewable Energy and Net Metering Regulations, 2020. The notification (No. 1204/D(T)/2019/KSERC) is dated 15 July 2022, appears in the Kerala Gazette Extraordinary of 18 July 2022, and the regulations take effect from 1 August 2022 (p1–2). Thirty amendment clauses rewrite the parent regulation clause by clause.

Clauses 1–7 (p2–4) reset scope and definitions: who the 2020 regulations apply to, what happens to entities still governed by the 2015 RE and 2014 grid-interactive solar regulations, new definitions of Average Power Purchase Cost, gross metering, Hydro Power Obligation and ocean energy, a restated settlement period, and a revised RPO trajectory extending the targets into FY 2022-23 and 2023-24 and adding HPO.

Clauses 8–15 (p4–6) rework the prosumer–licensee interface: prosumers may install RE capacity above their connected load or contract demand but lose the net-metering benefit; residential flats on LT domestic common services may net-meter up to 100 kW; a new Regulation 17A obliges the licensee to run an online application portal and publish procedures, single point of contact, charges and empanelled providers; acknowledgement, deemed-receipt and application-tracking timelines are prescribed; the licensee must upgrade distribution infrastructure needed for connectivity and pass through Central/State financial incentives.

Clauses 16–20 (p6–8) address tariff architecture: 'declared date of commercial operation' replaces 'commissioned'; generic tariff scope, capacity ceilings and non-redetermination of previously fixed tariffs; provisional tariff for projects commissioned between 1-4-2020 and 31-7-2022; and MUST RUN status for RE plants with Commission-approved PPAs.

Clauses 21–30 (p9–11) set O&M escalation, capital cost norms by solar capacity band, CUF for the balance of the control period, generic tariffs for solar up to 1 MW, a gross-metering option, extension of off-grid solar generation-based incentives to the end of the control period, a delay penalty cut to Rs 500 per day, and a replaced annexure list.

Annexures IV–VI (p13–17) carry the normative parameters and tariff computations for small hydro up to 2 MW, wind up to 5 MW and three solar capacity bands; the Explanatory Note (p18) records the consultation and the reasons for the amendment.

Standard name
Net Metering and Rooftop Solar, Renewable Energy Tariff Regulations, RPO Regulations
Primary topics
Net metering, Renewable energy tariff, Renewable purchase obligation (RPO / RCO)

Read with this

The regulation

Other copies of these documents (1)

3 more documents belong here and are not on Voltaic: 3 copies in another language.

Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on dev.erckerala.org ↗

Report an issue with this document