Renewable Energy & Net Metering Regulations, 2020 — Statement of Objections/Reasons
Draft Kerala State Electricity Regulatory Commission (Renewable Energy & Net Metering) Regulations, 2020
Statement of reasonsDate not stated
Replaced by Renewable Energy and Related Matters Regulations, 2025
See that regulation for the date it took effect and for anything it keeps in force.
The commission's reasons for the Renewable Energy and Net Metering Regulations, 2020 or one of its amendments.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken under the above Regulations shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”
Summary
Summary written by software, from pages 1 to 34 of 41. Check the regulator's original before you rely on it.
The document is KSERC's Statement of Objections / Reasons published with the draft Kerala State Electricity Regulatory Commission (Renewable Energy & Net Metering) Regulations, 2020/2019. It records the pre-publication consultation — website comments, Ernakulam stakeholder consultation on 18.09.2019 and public hearings at Thiruvananthapuram on 24.10.2019 and Ernakulam on 31.10.2019 — and then works through stakeholder objections and the Commission's clause-by-clause decisions (p1–2).
The SoR is not the regulation itself; it proposes modifications to the draft. It revises the definition of infirm power so pre-COD RE injection gets post-COD tariff only if the generator has an agreement with the licensee, otherwise SLDC settles at deviation settlement rates (p2–3). It declines to change peak/off-peak time blocks, which follow the 08.07.2019 tariff order (p3–4), and expands 'renewable source of energy' to include large hydro above 25 MW commissioned on or after 08.03.2019 (p4–5).
On RPO, it retains the draft trajectory for 2019-20 to 2021-22, leaves 2022-23 and 2023-24 for later notification (p5–7), excludes old large hydro from the RPO consumption base while not treating it as RE (p8–9), confirms that buyer/small licensees must meet RPO but urges KSEB Ltd to support them (p9–12), and exempts co-generation self-consumption from captive RPO following APTEL judgments (p12–13).
On net metering and charges, it retains a 1 MW net-metering ceiling with a 20 kW domestic proviso and grandfathering for existing prosumers (p13–15, p33–34), phases cumulative distributed RE interconnection at 75% of feeder/transformer capacity with review after two years (p15–17), retains 5% grid support and banking charges (p17–19), retains time-block adjustment limits of 80% for peak and 100% for other blocks (p19–22), and refuses general waivers of transmission/wheeling/losses for RE, while clarifying per-unit transmission charges for embedded captive consumers (p22–28). It retains accounting of prosumer/captive RE generation toward the distribution licensee's RPO and discusses REC ineligibility rather than sharing REC benefits (p28–32). The last issue addresses injection/drawal mismatch and proposes a new Regulation 22(2) for prosumers not under net metering (p32–34).
Read with this
The regulation
- Dated 7 Feb 2020Renewable Energy and Net Metering Regulations, 2020
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (2)
3 more documents belong here and are not on Voltaic: 3 copies in another language.