KSERC · Kerala State Electricity Regulatory Commission
Renewable Energy and Net Metering Regulations, 2020 — Second Amendment, 2024
Kerala State Electricity Regulatory Commission (Renewable Energy and Net Metering) (Second Amendment) Regulations, 2024
Amendment · Gazette copyDated 7 Aug 2024Published in the Gazette 16 Aug 2024In force from 1 Apr 2024No. 230/Con.Engg./2023/KSERC dated 7th August, 2024
Replaced by Renewable Energy and Related Matters Regulations, 2025
See that regulation for the date it took effect and for anything it keeps in force.
The Gazette copy of the Renewable Energy and Net Metering (Second Amendment) Regulations, 2024.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken under the above Regulations shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the second amendment to KSERC's 2020 Renewable Energy and Net Metering Regulations. It was issued on 7 August 2024, gazetted on 16 August 2024, and is brought into force retrospectively from 1 April 2024 (p1–2).
The operative part (clauses 1–2, pp1–7) rewrites the definitional base in Regulation 2 — adding Energy Storage Systems and Energy Storage Obligation, Wind Power Obligation, Other RPO, Pumped Storage Projects and Net-Billing/net feed-in, and substituting the definitions of Hydro Power Obligation, Renewable Energy System and Renewable Source of Energy (p2–4). A new Table 1(a) is inserted into Regulation 3, carrying the RPO trajectory across HPO, WPO, Other RPO, total RPO and ESO by financial year (p4). Regulation 4 is recast so distribution licensees meet RPO against both tables, with provisos on accounting self-generated RE, treating hydro other than post-2019 projects as Other RPO, and covering wind shortfalls from other buckets (p4–5). Regulations 5 and 6 are conformed for captive and open access consumers, including a proviso letting surplus solar count toward HPO or WPO (p5). Regulation 8 omits two sub-regulations and renumbers the remainder; Regulation 10 gains a proviso ring-fencing which instrument governs RPO for each financial-year vintage (p5–6). Regulation 13 gains an explanation on how solar plant capacity is measured for connectivity and on inverter safety standards; Regulation 14 caps distributed-energy interconnection against distribution transformer capacity and requires monthly transformer-wise publication (p6). Regulation 33 extends the control period (p7).
The Explanatory Memorandum (pp7–8) sets out the policy background: the MoP RPO trajectory order of 22 July 2022, the 500 GW non-fossil target, State Climate Change Action Plan 2.0, the Electricity (Rights of Consumers) Rules, ANERT's request on transformer loading, and the consultation history.
Read with this
The regulation
- Dated 7 Feb 2020Renewable Energy and Net Metering Regulations, 2020
Amendments and corrections
Commencement notices and reasons
Other copies of these documents (1)
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.