HPERC · Himachal Pradesh Electricity Regulatory Commission

Grant of Connectivity, Long-term and Medium-term intra-State Open Access and Related Matters Regulations, 2010 — Third Amendment, 2024

Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium–term intra-State Open Access and Related Matters) (Third Amendment) Regulations, 2024

AmendmentDated 15 Feb 2024No. HPERC/418 dated 15th February, 2024

Amends the Grant of Connectivity and Long-term and Medium-term Intra-State Open Access Regulations, 2010.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Himachal Pradesh Electricity Regulatory Commission's Third Amendment to its 2010 regulations on connectivity and intra-State open access, notified at Shimla on 15 February 2024 as No. HPERC/418 (p1). It is a two-page, two-clause amending instrument.

Regulation 2 (p1) substitutes the table in Regulation 6 of the 2010 Regulations, which prescribes application fees for connectivity and for medium-term and long-term open access. The replacement table bands applicants by the quantum of power to be injected into or drawn from the State transmission or distribution system, with separate columns for connectivity, medium-term open access and long-term open access fees, and carves out solar PV and biomass projects as their own category at the lowest capacity band.

Regulation 3 (p2) substitutes the table in Regulation 7, which prescribes time limits for processing applications. It distinguishes connectivity for solar PV and biomass projects, connectivity for other projects by capacity and category, medium-term open access and long-term open access — the last of these having different limits depending on whether augmentation of the transmission or distribution system is required.

The amendment takes effect on publication in the Rajpatra, Himachal Pradesh (p1); no gazette date is printed. It amends the 2010 Regulations as already amended in 2012 and 2021 (p1).

Standard name
Open Access Regulations, Connectivity and GNA Regulations
Primary topics
Open access, Connectivity and GNA

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document