HPERC · Himachal Pradesh Electricity Regulatory Commission
Grant of Connectivity and intra-State Open Access Regulations, 2010 — First Amendment — Order, 2012
In the matter of draft regulations of First Amendment to the Himachal Pradesh Electricity Regulatory Commission (Grant of Connectivity, Long-term and Medium–term intra –State Open Access and Related Matters) Regulations, 2010.
OrderDated 3 Dec 2012Published in the Gazette 10 Oct 2012
Read with the Grant of Connectivity and Long-term and Medium-term Intra-State Open Access Regulations, 2010.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The order closes HPERC's consultation on the draft First Amendment to its 2010 intra-State open access regulations and records the changes the Commission wants carried into the final text (p1, p10). It states that the draft was issued on 9 October 2012, published in the Rajpatra on 10.10.2012 and in The Tribune and Amar Ujala on 12.10.2012, with objections due 1 November 2012 and extended to 19 November 2012 (p1).
Paragraphs 2–4 set the frame: section 42 of the Electricity Act 2003 requires the State Commission to introduce open access in phases, with the fifth proviso setting a January 2009 milestone for consumers above 1 MW; the 2005 Open Access Regulations (open access from FY 2007-08 above 1 MVA contract demand) were replaced by the 2010 Regulations, which dropped any threshold; HPSEB's unbundling into separate distribution, transmission and load despatch entities left gaps; and the amendment aims to simplify procedures and rationalise fees and bank guarantees (pp1–3).
Eight stakeholders commented, including HPSEB Ltd., the SLDC and three industrial associations (p3). The associations attacked the very concept of mandatory 'deemed' open access and cited a Madhya Pradesh Commission order; HPSEB Ltd. and the SLDC said they were not ready and asked for deferral; others called the draft impracticable and hard to follow (pp3–4). The Commission's general findings reply that the amendments do not impose mandatory or deemed open access, that the Ministry of Power letter of 30.11.2011 has no bearing, and that tariff for open access consumers belongs in tariff proceedings (pp4–5). It directs deletion of the 'entitled consumers' provisions, revision of the 'deemed open access' wording, and integration of draft regulation 33-B with 3-A (pp5–6). Eligibility is pegged to contract demand of 1 MVA rather than connected load, while scheduling stays in MW (pp7–8); consumers below 1 MVA may be given access on merit to buy renewable energy (p6).
Paragraphs 7.1–7.14 give regulation-by-regulation findings: some suggestions are rejected (definition of consumer, two-month dues limit, the 1 MW distribution-system limit, review of regulation 27 charges), others accepted (energy losses in kind clarified, 33-D and 33-F deleted in favour of the detailed procedure under regulation 26, 33-C, 33-E and 33-J rationalised, standby power scope explained, metering confined to the consumer end) (pp6–10). It ends by directing that the changes be made and the final regulations issued accordingly (p10).
Read with this
The regulation
Amendments and corrections
- Dated 7 Dec 2012Grant of Connectivity, Long-term and Medium-term intra-State Open Access and Related Matters Regulations, 2010 — First Amendment, 2012
- Dated 11 Aug 2021Grant of Connectivity and Long-term/Medium-term intra-State Open Access Regulations, 2010 — Second Amendment, 2021
- Dated 15 Feb 2024Grant of Connectivity, Long-term and Medium-term intra-State Open Access and Related Matters Regulations, 2010 — Third Amendment, 2024
Commencement notices and reasons
Procedures and orders made under it
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.