Unscheduled Interchange Charges and Related Matters Regulations, 2009

Central Electricity Regulatory Commission (Unscheduled Interchange charges and related matters) Regulations, 2009

RegulationDated 30 Mar 2009In force from 1 Apr 2009No.L-1(1)/2009-CERC dated New Delhi, the 30th March 2009

Replaced by Deviation Settlement Mechanism and related matters Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's principal regulation on Unscheduled Interchange (UI) charges — notified on 30 March 2009 and brought into force on 1 April 2009 under Section 178 of the Electricity Act, 2003 (p1). Its stated objective is to keep grid discipline through a commercial mechanism that prices deviations from schedule (p3), and it applies to generating stations and their beneficiaries, and to sellers and buyers transacting through open access / medium-term / long-term access in inter-State transmission (p4).

Regulation 5 sets the price curve: a UI rate per kWh keyed to the average frequency of each 15-minute time-block across the operating band, payable by over-drawing buyers/beneficiaries and under-injecting generators/sellers and receivable by those deviating the other way, with a special cap for stations using coal, lignite or APM gas, and a commitment to review the rates at least six-monthly through separate orders (p4–5). Regulation 6 leaves declaration of capacity, scheduling and the elimination of gaming to the Grid Code and the Open Access Regulations 2008, adds a tolerance band for non-hydro stations and a day-plus-3 scheduling route for hydro compensation (p5–6).

Regulation 7 caps deviation volumes per time-block and on a daily aggregate, adds an Additional UI Charge when frequency falls below 49.2 Hz, preserves action under Sections 142 and 149, and requires RLDCs to publish monthly UI accounts (p7–8). Regulation 8 makes RLDC instructions override Regulations 6 and 7 (p9). Regulations 9 to 11 route all receipts into the UI Pool Account Fund, set the payment and payout timetable with interest on delay, and allow the surplus to fund strategic transmission schemes and ancillary services on Commission approval (p9–11). Regulations 12 and 13 give the Commission power to relax and to amend (p11).

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement, Scheduling and despatch

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.