Unscheduled Interchange Charges and Related Matters (Second Amendment) Regulations, 2012

Central Electricity Regulatory Commission (Unscheduled Interchange charges and related matters) (Second Amendment) Regulations, 2012

AmendmentDated 5 Mar 2012In force from 2 Apr 2012No.L-1(1)/2011-CERC dated the 5th March, 2012

Replaced by Deviation Settlement Mechanism and related matters Regulations, 2014

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Unscheduled Interchange Charges and Related Matters Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the second amendment by the Central Electricity Regulatory Commission to its 2009 Unscheduled Interchange (UI) charges and related matters regulations, issued 5 March 2012 and brought into force from 2 April 2012 (p1). It does two things: it substitutes the whole of Regulation 5 on UI charges, and the whole of Regulation 7 on limits on UI volume and the consequences of crossing them (p1–2, p6).

Substituted Regulation 5 restates who pays and who receives UI charges, fixes the pricing basis on average time-block frequency, and then carves out a set of Cap Rate situations — coal/lignite/APM-gas stations deviating from schedule, non-hydro stations injecting beyond declared capacity, buyer under-drawal beyond a schedule/MW threshold, seller over-injection beyond schedule and installed-capacity limits, and injections beyond ex-bus installed-capacity limits (p1–3, p5). It then gives the methodology for building the frequency-linked UI price vector, with anchor points at the top and bottom of the frequency band, and provides for six-monthly review and re-notification of Schedule A, and for payment of infirm power injected during testing before COD (p3–6). Inter-regional UI between asynchronous regions is to be computed by the Regional Power Committees and settled at the average of the two regions' charges (p6).

Substituted Regulation 7 sets volume limits on over-drawal and under-injection below a threshold frequency, on both a time-block and daily aggregate basis, with an explanation extending the limit to all intra-State entities at the State boundary (p6–7). Below a lower frequency threshold, an Additional UI Charge is layered on top of the ordinary UI charge, at percentages the Commission is to specify with reference to grid-discipline behaviour, and Schedule A now fixes those percentages in frequency steps (p7–8, p13–14). Regulation 7 also preserves the Commission's power to act under s.142 of the Act, allows it to prescribe additional charges in further frequency bands, and requires RLDCs to publish monthly UI accounts disaggregated by frequency band (p8–9).

Schedule "A" (p10–14) is the operative price annexure: a frequency-step UI rate vector, the category-wise cap rates, cap rates for infirm power by fuel type, and the additional UI charge percentages.

Standard name
DSM Regulations
Primary topics
Deviation settlement (DSM), Energy accounting and settlement

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document