Draft RE Tariff Regulations, 2020 — Explanatory Memorandum

Explanatory Memorandum On Draft Central Electricity Regulatory Commission (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020

Explanatory memorandum to a draftReleased with the draft dated 28 Apr 2020

Draft

The draft has since been finalised as the RE Tariff Determination Regulations, 2020.

Explanatory memorandum to the Terms and Conditions for Tariff determination from Renewable Energy Sources Regulations, 2020 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Explanatory Memorandum of May 2020 (p1) setting out the reasoning behind the draft CERC (Terms and Conditions for Tariff Determination from Renewable Energy Sources) Regulations, 2020, which are to govern tariff norms for the control period beginning 1 July 2020. It is not a regulation. Each chapter quotes the corresponding provision of the RE Tariff Regulations, 2017, compares it against what SERCs, lenders (IREDA, PFC) and actual projects show, and states what the Commission proposes to keep, change or newly add (p7, p10–12).

Chapter 1 explains CERC's statutory role and the history of RE tariff regulations across earlier control periods, notes the order of 24 March 2020 extending the 2017 regulations to 30 June 2020, and describes the project data received from IREDA, PFC, NIWE and POSOCO that underpins the norms (p7–9). Chapter 2 sets out applicability under Section 79 read with Section 62, the Tariff Policy direction that CERC tariff acts as a ceiling where procurement is not bid out, retention of existing eligibility criteria, and the plan of the memorandum (p10–12).

Chapter 3 covers general principles: continuation of a three-year control period, tariff period equal to useful life, which technologies keep generic tariff and which move to project-specific tariff, the petition and beneficiary-consent process, the single-part/two-part tariff structure, levellisation using post-tax WACC, and a new treatment for over-generation above normative CUF/PLF (p13–18). Chapter 4 sets the financial principles — normative debt-equity, return on equity and MAT grossing-up, loan tenure, interest rate, depreciation, interest on working capital, O&M escalation, rebate and late payment surcharge, treatment of subsidy/incentive, and pass-through of statutory charges (p19–30).

Chapter 5 is the bulk: technology-wise parameter sections, each reviewing capital cost, CUF/PLF, auxiliary consumption, heat rate or fuel consumption, calorific value, fuel price and O&M for wind (including offshore), small hydro, biomass on Rankine cycle, non-fossil-fuel cogeneration, solar PV/thermal/floating, biomass gasifier, biogas, MSW and RDF, and first-time frameworks for renewable hybrid projects and renewable energy with storage (p31–80).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Capital cost and investment

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.