Skip to content

CERC · Central Electricity Regulatory Commission

Power System Development Fund Regulations, 2014 — Draft

Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2014

Draft regulationDated 28 Feb 2014No. L-1/148 /2014/CERC dated 28th February, 2014

Draft

A proposal that has since been finalised as the Power System Development Fund Regulations, 2014.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft notification dated 28 February 2014 (p1) in which the Central Electricity Regulatory Commission proposes the Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2014, numbered L-1/148/2014/CERC. It is made under the Electricity Act, 2003 and would take effect from the date of publication in the Official Gazette (p1).

Regulations 1–2 (p1–2) give the short title, the commencement rule and the defined terms, most of which borrow meanings from the Congestion Relief Regulations, the Power Market Regulations, the Deviation Settlement Mechanism Regulations and the Grid Code. Regulation 3 (p2–3) constitutes the PSDF and identifies the streams that feed it — residual congestion charges, congestion amount from market splitting, residual deviation settlement charges, RLDC reactive energy charges and any other charges the Commission notifies — to be transferred periodically by the collecting agencies and held in the Public Account of India.

Regulation 4 (p3–4) lists what the fund may be spent on: strategically important transmission, reactive compensation for voltage profile, protection schemes and protection audits, renovation and modernisation of transmission and distribution to relieve congestion, and studies or capacity building. Distribution utility projects qualify only if not covered by other Government of India schemes, and private sector projects are excluded outright.

Regulations 5–8 (p4–6) build the institutional machinery: NLDC as Nodal Agency and secretariat, a Ministry of Power Appraisal Committee for techno-economic scrutiny and prioritisation, and an inter-ministerial Monitoring Committee chaired by Secretary (Power) for sanction, release and monitoring. They also lay down the sequence — proposal to the Nodal Agency, appraisal, petition for regulatory approval by the Central or State Commission, administrative sanction, then release of funds.

Regulations 9–13 (p6–7) cover grant-based assistance with quantum left to guidelines, execution and O&M responsibility on the project entity, budget, accounting and audit through a Detailed Procedure, the implementing agencies, and an annual report with audited accounts to the Central Government and the Commission, laid before Parliament. Regulations 14–15 (p7) give the Commission power to remove difficulties and repeal the 2010 PSDF Regulations with a savings clause.

Primary topics
Power System Development Fund (PSDF), Congestion and curtailment, Deviation settlement (DSM)

Read with this

The regulation

Amendments and corrections

Commencement notices and reasons

Other copies of these documents (2)

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document