CERC · Central Electricity Regulatory Commission

Power System Development Fund (First Amendment) Regulations, 2015

Central Electricity Regulatory Commission (Power System Development Fund) (First Amendment) Regulations, 2015

AmendmentDated 3 Jul 2015In force from 1 Jun 2015No. L-1/148/2014/CERC dated 3rd July, 2015

Replaced by Power System Development Fund Regulations, 2019

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Power System Development Fund Regulations, 2014.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, annual reports, confirmation or declaration or any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A single-page CERC notification amending the Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2014. It is made under Section 178(1) and 178(2)(ze) of the Electricity Act, 2003 and was issued on 3 July 2015, but comes into force retrospectively from 1 June 2015 (p1).

Regulation 1 gives the short title and commencement (p1). Regulation 2 inserts a new clause (3A) after clause (3) of Regulation 4 of the Principal Regulations (p1). The inserted clause is a non-obstante provision: any scheme sanctioned by the Central Government in the interest of development of the power system that requires PSDF support as part of the scheme is made eligible for assistance from the Fund (p1). Its practical effect is to widen eligibility beyond whatever Regulation 4 previously contemplated, without disturbing the existing clauses.

The notification also carries a note recording that the Principal Regulations were published on 10 June 2014 in the Gazette of India Extraordinary Part III-Section 4 at Serial No.171 (p1). There is no separate statement of reasons, and no text on who administers or disburses the assistance.

Primary topics
Power System Development Fund (PSDF)

Read with this

The regulation

Commencement notices and reasons

Other copies of these documents (2)

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.