Skip to content

DERC · Delhi Electricity Regulatory Commission

Group Net Metering and Virtual Net Metering Guidelines under Net Metering for Renewable Energy Regulations, 2014 — Draft

Draft Guidelines under DERC (Net Metering for Renewable Energy) Regulations, 2014 for Implementation of Group Net Metering and Virtual Net Metering Framework under Delhi Solar Policy 2016

Draft guidelinesDated 17 Dec 2018

Draft

A proposal, not law. Voltaic holds no final regulation made from this draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

These are DERC guidelines that create the operating framework for two new solar arrangements — Group Net Metering (GNM) and Virtual Net Metering (VNM) — under the Commission's 2014 Net Metering Regulations and the GoNCTD Delhi Solar Policy, 2016 (p1). They are issued under Regulation 14 of the 2014 Regulations and take effect from the date of issue (p1). A committee constituted by the Commission prepared the framework; its report is cited as Annexure-I (p1).

Clause 1 defines both arrangements and sets the common procedural spine (p1–3). GNM lets surplus solar exported from a plant be adjusted against one or more other service connections of the same consumer inside a single DISCOM territory; VNM lets consumers without a usable roof hold a declared share of a collectively owned plant and receive pro-rata credits. Rollout is phased: both frameworks apply initially only to government entities, extendable to other Delhi consumers by Commission direction or order (p2). Ancillary matters are deferred to existing instruments — annual settlement rate to the Net Metering Guidelines, land space to the Supply Code and Performance Standards Regulations, 2017, and forecasting/scheduling/deviations to applicable regulations or directions (p2). Applications go to the DISCOM on its prescribed form with a fee, and permission is to issue within a stated window after feasibility (p2).

Clause 2 details GNM (p3–4): treating separately-named connections of state/central government departments as one consumer, differential SLD charges where plant capacity exceeds sanctioned load, DISCOM-funded smart meters at generation points, an annual adjustment-priority list with a two-month advance notice defaulting to last year's order, ToD-compliant metering, itemised billing of exports, imports, net units and carry-forward, netting of prior credits before invoicing, kWh-to-kWh offsetting with unity power factor for kVAh billing, and year-end payment for unadjusted credits at Commission-notified rates.

Clause 3 mirrors that for VNM (p4–6) and adds the credit-share mechanism based on declared beneficial ownership, a once-a-year option to change shares, and inter-DISCOM transfer with normative distribution losses borne by the consumer and year-end settlement under the 2014 Regulations (p6).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Metering, Billing and payment

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on derc.gov.in ↗

Report an issue with this document