Net Metering for Renewable Energy Regulations, 2014

Delhi Electricity Regulatory Commission (Net Metering for Renewable Energy) Regulations, 2014

RegulationDated 2 Sep 2014No. F. 9(116)/DERC/Tariff/DS/2013-14/C.F 4110/ dated 2 nd September, 2014

4 amendments to it are on Voltaic, the latest dated 16 Jul 2026.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

DERC's Net Metering for Renewable Energy Regulations, 2014 create the framework under which a consumer of a Delhi distribution licensee may install a renewable energy system at its premises and connect it to the licensee's network, with import and export recorded through a net meter. The notification is dated 2 September 2014 and comes into force on Gazette publication (p1, p8); the Gazette date itself is not printed.

Regulations 2 and 3 fix the vocabulary and interpretation rules, borrowing load and supply-code concepts from the DERC Supply Code and Performance Standards Regulations, 2007, the REC framework from CERC and renewable source recognition from MNRE (p1–3). Regulation 4 confines the scheme to consumers who buy from the licensee, plus the licensee itself (p3).

The operating core is Regulations 5 to 9 (p3–7). Connectivity is first-come-first-serve subject to operational constraints and to transformer-level capacity the Commission may specify; licensees must publish available transformer capacity on their websites within a month and refresh it annually. Installed capacity is bounded by interconnection feasibility, the consumer's service line and sanctioned load, with service-line-cum-development charges payable on any capacity above sanctioned load, and a minimum size applies. Applications and registration sit with the licensee under Commission-issued guidelines and fees (p4–5). Regulation 7 ties interconnection to the CEA distributed-generation connectivity and safety regulations, permits battery-backed systems with anti-islanding wiring and a manual isolation switch, splits operation and maintenance responsibility at the net meter, and gives the licensee a disconnection right (p5–6). Regulation 8 governs meter standards, accuracy, ownership, cost, location and ToD compliance (p6). Regulation 9 sets billing and energy accounting: separate display of imported, exported and net units, carry-forward of surplus as energy credit within a settlement period, netting before invoicing, kWh-to-kWh offsetting with unity power factor assumed for kVAh consumers, and payment for year-end unadjusted credits at Commission-notified rates, with no deemed generation (p6–7).

Regulation 10 exempts net-metered systems from wheeling, banking, cross-subsidy and other charges for five years unless extended (p7). Regulations 11 and 12 link the scheme to the CERC REC framework and let the licensee count this generation toward its RPO where the generator is not itself an obligated entity (p7). Regulation 13 makes violations penalizable in an amount the Commission decides, with compensation possible; Regulations 14 to 16 reserve powers to direct, relax and amend (p8).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Metering, Billing and payment

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of DERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.