HPERC · Himachal Pradesh Electricity Regulatory Commission
DSM Second Amendment Regulations, 2021 — Finalisation Order
Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Second Amendment) Regulations, 2021.
OrderDated 7 Sep 2021
Replaced by Deviation Settlement Mechanism and Related Matters Regulations, 2024
See that regulation for the date it took effect and for anything it keeps in force.
Made under the Deviation Settlement Mechanism and Related Matters Regulations, 2018.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation, settlement of dues and requirement for opening of the Letter of Credit etc.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is HPERC's order of 7 September 2021 disposing of objections and suggestions on the draft Himachal Pradesh Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) (Second Amendment) Regulations, 2021, and directing finalisation of the amendment (p1, p7). It is a reasons-and-decision document, not the amended regulation text.
The order first recaps the regulatory lineage: HPERC's DSM Regulations were issued in 2018 and amended in 2019, and the exercise is meant to align them with CERC's DSM Regulations, as amended from time to time (p1). It records pre-publication consultation on the draft, including publication in the Rajpatra and newspapers, and submissions from HPPCL, HPSLDC, HPSEBL and IEX (pp1–2).
The operative part is section 5. On regulation 1, HPERC refuses HPSEBL's request to bring the amendments into force from 03.12.2018, holding that they will have prospective effect only (p2). On regulation 7, it addresses additional deviation charges and accepts SLDC's clarification that distribution licensee under-drawal beyond 12% of scheduled drawal should attract zero charges, with a proviso tied to a 300 MW schedule threshold (pp2–3). On regulation 8, it similarly accepts SLDC's clarified wording on over/under-drawal limits in the specified frequency band (p3). On the 300 MW threshold, it rejects HPSEBL's plea for 400 MW, noting that CERC's 400 MW applies to the State's net schedule, not individual entities (p4).
Section 5.5 deals with the proposed Schedule. HPERC retains its draft approach on scheduling and DSM settlement rather than IEX's alternative, retains provisions on inter-state transaction treatment, and corrects typographic omissions in draft table 5 so that solar/wind deviation charges beyond 35% are Rs. 1.50 per unit (pp4–5). In miscellaneous comments, it declines special DSM treatment for hydro unless CERC changes its regulations, declines run-of-river and cap-rate pleas as outside the proposal, and refers solar/wind forecasting and scheduling issues to the HP Grid Code Review Committee (pp5–6). It directs HPSEBL to take DSM account mismatches up with SLDC (p7). Section 5.7 records no further comments, and the Commission finalises the amendment with minor modifications and directs notification (p7).
Read with this
The regulation
- Dated 16 Oct 2018Deviation Settlement Mechanism and Related Matters Regulations, 2018
Amendments and corrections
Commencement notices and reasons
Earlier drafts
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.