Delhi Electricity Supply Code & Performance Standards Regulations 2007 — Explanatory Note

Explanatory Note on Delhi Electricity Supply Code & Performance Standards Regulations 2007.

RegulationDated 18 Apr 2007

Replaced by Delhi Supply Code and Performance Standards Regulations, 2017

See that regulation for the date it took effect and for anything it keeps in force.

Read with the Delhi Electricity Supply Code and Performance Standards Regulations, 2007.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or action taken or purported to have been taken, or proceedings initiated under such repealed Regulations, shall be deemed to have been taken under these Regulations to the extent that same were not inconsistent with the Act.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is DERC's explanatory note accompanying the final Delhi Electricity Supply Code & Performance Standards Regulations 2007. It is not the operative regulation text; it explains how the Commission finalised the Supply Code and performance standards for distribution licensees in the National Capital Territory of Delhi, and why it accepted, rejected or modified stakeholders' suggestions (p1). The opening states the object: a standardised supply code and performance standards for distribution and retail supply licensees in Delhi (p1).

Pages 1–2 record pre-consultation: the draft was posted and published in newspapers on 22.5.2004, copies were sent to the licensees (DTL, NDPL, BRPL, BYPL) and NDMC and to the Principal Secretary (Power), GNCTD on 24.5.2004, and public hearings followed on 12.12.2005 and 17.2.2006. Pages 2–4 summarise responses. Licensees asked for a transition period, phased implementation, a 60-day grace before compensation, revision of miscellaneous charges, and repeal of older metering/billing and miscellaneous-charge provisions. The Commission declined phased implementation, saying the Regulations should be implemented forthwith except where Schedule III provides time frames, and that the standards build on the 2002 metering and billing performance standards (p3–4).

The bulk, “Notes on Some Important Clauses” (p4–12), explains changes from the draft. It records revised or dropped definitions in Regulation 2 (p4–5); changes to Chapter II on system of supply and classification, including voltage limits and Railway/DMRC connections (p5); Chapter III on new and existing connections, including the sub judice outstanding-dues clause retained pending the Apex Court, temporary connections and security deposits (p6–7); Chapter IV on agreements, registration/processing fees, security deposits, development charges and service-line charges, and meter-testing charges (p7–9); Chapter V on metering and billing, CEA meter regulations, internal wiring and bill particulars (p9–10); Chapter VII on theft and unauthorised use, including assessment procedure under the Ministry of Power removal-of-difficulties order (p10–11); Chapter VIII on complaint handling and street-light complaints (p11); and Chapter X on notices, force majeure, relaxation powers and repeals/savings (p11–12). A closing section explains that most compensation is automatic, but compensation for Section 43 violations is payable only after hearing the licensee (p12).

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
Conditions of supply, Standards of performance, New connections and load changes

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.