Regulation of Power Supply (First Amendment) Regulations, 2020 — Explanatory Memorandum — Draft

Draft Central Electricity Regulatory Commission (Regulation of Power Supply) (First Amendment) Regulations, 2020

Explanatory memorandum to a draftDated 16 Jul 2020L-1/42/2010-CERC dated 16.07.2020

Draft

The draft has since been finalised as the Regulation of Power Supply Regulations, 2010 — First Amendment, 2021.

Explanatory memorandum to the Regulation of Power Supply (First Amendment) Regulations, 2020 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Commission proposes a first amendment to the CERC (Regulation of Power Supply) Regulations, 2010 and explains why in this explanatory memorandum (p1). The driver is alignment: the 2010 Regulations measure default and outstanding dues against a 60-day payment window, while the CERC (Terms and Conditions of Tariff) Regulations, 2019 (control period 2019-2024) and the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations, 2020 both use 45 days from presentation of bills (p1–2).

Paragraphs 3–6 recite the existing definitions of "Default Trigger Date" and "Outstanding dues" and propose to recast both around a new defined "Due date", inserted as Regulation 2(1)(e-i). The definitions of "Beneficiary" and "Defaulting entity" are to be modified, and the definition of "User" deleted (p2–3).

Paragraphs 7–8 explain that the 2020 Sharing Regulations authorise the CTU to bill, collect and disburse transmission charges and to invoke regulation of power supply under the 2010 Regulations. A new clause (1A) would extend references to "transmission licensee" to include the CTU (p3).

Paragraphs 9–10 propose amending Regulation 3 so that regulation of power can be invoked where a provision exists either in the agreement between generator/transmission licensee and beneficiary or in the applicable CERC regulations, and adding "or applicable Regulations" after "Agreement" in Regulation 4 (p3–4).

Paragraphs 11–15 propose clarifying Regulation 5 (service of notice and request for an implementation plan), correcting the status of the entity in Regulations 6 and 12(1), substituting "withdrawal or postponement" for "cancellation" in Regulation 8, replacing references to the repealed Unscheduled Interchange Regulations, 2009 with the Deviation Settlement Mechanism Regulations, 2014 in Regulations 11(1), 14 and 18, and deleting Regulation 12(2) (p4).

Primary topics
Payment security, Late payment surcharge and rebate

Read with this

The regulation

Commencement notices and reasons

Other copies of these documents (2)

One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document