Security Deposit Regulations, 2005 — Third Amendment, 2020 — Explanatory Memorandum — Draft

Explanatory Memorandum for draft of Himachal Pradesh Electricity Regulatory Commission (Security Deposit) (Third Amendment) Regulations, 2020.

Explanatory memorandum to a draftDated 15 Feb 2020

Draft

The draft has since been finalised as the Security Deposit Regulations, 2005 — Third Amendment, 2020.

Explanatory memorandum to the Security Deposit Regulations, 2005 — Third Amendment, 2020 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Himachal Pradesh Electricity Regulatory Commission's explanatory memorandum for the draft HPERC (Security Deposit) (Third Amendment) Regulations, 2020 (p1). It explains why the Commission proposes to amend the HPERC (Security Deposit) Regulations, 2005, following HPSEBL's proposals to the Hon'ble High Court of Himachal Pradesh and the High Court's order dated 20.11.2019 that the proposals require the Commission's approval (p1). The memorandum does not reproduce the draft regulations; it records the Commission's reasoning and the changes it proposes (pp1–2).

It addresses four issues. First (pp2–4), the rate of initial security deposit. The Commission rejects applying the LDHF formula from the HP Electricity Supply Code, 2009 in full because that formula is meant for theft assessment and its categories do not align with tariff categories. It proposes a new formula for per-kW/kVA initial security deposit, using load or contract demand, average working days, average hours of use, demand factor, average tariff, and the number of billing months plus a fixed add-on. A table supplies the days, hours and demand-factor values by consumer category (p4). The memorandum also proposes a uniform procedure for HPSEBL and retains the 50% relief for BPL beneficiaries (p4).

Second (pp4–5), it proposes to raise the amount existing consumers must maintain from one billing cycle to a longer formula period and to elaborate the annual review and additional-security-deposit process. A cap is proposed: where additional deposit exceeds 30% of average monthly bills of the preceding twelve billing months, recovery through demand notice in any three-month period is limited to that percentage, with the balance in later quarters; the cap does not apply to consumers on the licensee's poor-credit-rating list (p5).

Third (p6), on mode of recovery, the Commission declines HPSEBL's cash-only proposal. It proposes to raise the threshold above which a consumer may opt for a bank guarantee instead of cash from 10 lacs to 25 lacs, and to make bank-guarantee encashment provisions more specific; existing bank-guarantee holders are not forced to convert unless they default on renewal (p6).

Fourth (p7), on refund, it proposes that on permanent reduction of connected load or contract demand the deposit be recalculated at current rates for the reduced load, with only the excess refunded, preferably by releasing the bank guarantee (p7).

Standard name
Security Deposit
Primary topics
Security deposit

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.