Terms and Conditions for Tariff Determination from Renewable Energy Sources Regulations, 2017

Central Electricity Regulatory Commission (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2017

Regulation · Gazette copyDated 17 Apr 2017Published in the Gazette 17 Apr 2017In force from 1 Apr 2017No.: 1/21/2017-Reg.Aff./(RE-Tariff - 2017-20)/CERC. dated 17th April 2017

Replaced by RE Tariff Determination Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

The Gazette copy of the RE Tariff Regulations, 2017.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's principal framework for setting tariffs for grid-connected renewable energy generation, notified on 17 April 2017 with retrospective commencement from 1.4.2017 and a stated life of three years unless reviewed or extended (p23). It applies to generating stations and units commissioned during the control period (first year FY 2017-18) whose tariff the Commission determines under s.62 read with s.79 of the Electricity Act, and it lists per-technology eligibility conditions — new plant and machinery, state-nodal-approved sites, MNRE-approved technologies, and a 25 MW ceiling for small hydro (p26–27).

Chapter 1 sets the general machinery: the three-year control period, tariff periods matched to technology useful life, which technologies get project-specific rather than generic tariff, how petitions for determination are filed, the structure and levellisation of tariff, and despatch treatment of renewable plants as must-run except larger biomass and cogeneration (p27–28). Chapter 2 lays down the financial principles — capital cost scope, debt-equity treatment, loan tenure and interest-rate benchmark, depreciation, return on equity, working capital, CUF/PLF calculation, O&M expense treatment and escalation, rebate, late payment surcharge, sharing of CDM proceeds, treatment of subsidies/incentives and taxes (p28–30).

Chapters 3 to 11 then give, technology by technology — wind, small hydro, biomass Rankine, non-fossil cogeneration, solar PV, solar thermal, biomass gasifier, biogas, and MSW/RDF — the norms for capital cost, CUF or PLF thresholds, auxiliary consumption, station heat rate, fuel mix and fossil-fuel limits, calorific value, fuel price, and O&M expenses (p31–37). Chapter 12 permits tariff to be agreed in deviation from the norms within a levellised-tariff ceiling, and preserves the Commission's power to relax provisions (p37). The Appendix carries the four petition forms and tariff-computation worksheets (p38–41).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Capital cost and investment

Read with this

The regulation

Commencement notices and reasons

Procedures and orders made under it

Earlier drafts

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.