Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2012 — Second Amendment, 2016
Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (Second Amendment) Regulations, 2016
AmendmentDated 11 Apr 2016No. HPERC/428 dated the 11th April, 2016
Replaced by Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2012.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Himachal Pradesh Electricity Regulatory Commission's Second Amendment to its 2012 renewable-energy tariff regulations, notified at Shimla on 11 April 2016 under No. HPERC/428 (p1). Its purpose is to bring municipal solid waste (MSW) and refuse-derived fuel (RDF) based power projects into the State's renewable-energy tariff framework and to give them distinct regulatory treatment.
Paragraph 2 (p1–2) widens Regulation 2: it defines MSW and RDF and expands "renewable energy sources" to cover urban or municipal waste, MSW and RDF based projects, and other sources approved by MNRE. Paragraph 3 (p2) rewrites the proviso to Regulation 3 so that a listed set of technologies — wind, small hydro, biomass on Rankine cycle, non-fossil fuel cogeneration, solar PV and thermal, biomass gasifier, biogas, MSW and RDF — are covered only if the Regulation 4 eligibility criteria are met. Paragraph 4 (p2) adds clauses (h) and (i) to Regulation 4, specifying what makes a project MSW-based or RDF-based: new plant and machinery on Rankine cycle technology using MSW or RDF as fuel.
Paragraph 5 (p2) adds a second proviso to Regulation 8 requiring the distribution licensee to compulsorily procure 100% of power from waste energy plants in the State and excluding those plants from competitive bidding for tariff determination, citing the Ministry of Power Tariff Policy of 28 January 2016. Paragraph 6 (p2) replaces Regulation 14(1)(iv): financial norms for MSW and RDF projects follow the Commission's adoption under Regulation 17(3A), while other cases keep the Chapter IV ceiling norms except capital cost. Paragraph 7 (p3) amends Regulation 17 — MSW and RDF projects join the class in sub-regulation (1)(v), and a new sub-regulation (3A) lets the Commission adopt Central Commission norms (useful life, tariff period, technology-specific and financial norms, tariff applicability, generic levellised tariffs with and without accelerated depreciation, treatment of grant-in-aid, subsidy and CDM benefits) for such projects.
The regulations come into force on the date of publication in the Rajpatra, Himachal Pradesh; that date is not printed in this text (p1).
Read with this
The regulation
Amendments and corrections
Commencement notices and reasons
Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.