Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2012 — First Amendment, 2015

Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (First Amendment) Regulations, 2015

AmendmentDated 11 Feb 2015No. HPERC-428 Vol-VIII dated the 11th Feburary, 2015

Replaced by Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

Notification of the First Amendment to HPERC's 2012 renewable-energy tariff regulations, issued from Shimla on 11 February 2015 under file No. HPERC-428 Vol-VIII (p1).

Pages 1–2 carry the operative amending regulations. Regulation 1 gives the title and the commencement rule — in force from publication in the Rajpatra, Himachal Pradesh, with the Gazette date not printed. Regulation 2 substitutes the second proviso to regulation 17(2) so that the Commission may, by order, categorise renewable projects other than SHPs by technology, capacity and available subsidy schemes, and may follow CERC's technology-specific parameters (including capital cost) mutatis mutandis for smaller capacities, capped at 5 MW for any one technology, for the financial years of the control period ending 31 March 2017 (p1); it also adds a proviso to regulation 17(3) letting the Commission fix annual ceiling rates and terms for licensee reverse bidding (p2). Regulations 3 and 4 add provisos to regulations 23(2)(b) and 26(4) setting the normative interest rate, where tariff is determined on a financial-year basis, as SBI's average base rate over the first six months of the previous year plus 300 and 350 basis points respectively (p2).

Pages 3–7 are the Commission's order and statement of reasons: the 2012 principal regulations were notified on 17 December 2012; the draft amendment was published on 1 January 2015 and advertised in two newspapers on 3 January 2015, with 30 days for objections (p3–4). Comments came from HP Power Corporation, HIMURJA and the Directorate of Energy. The Commission declined the Directorate's suggestions to sub-categorise solar and wind at 500 kW and to lower the reverse-bidding threshold accordingly, holding the amendment to be technology-neutral and merely enabling, and not a deviation from the State Solar Policy or the Section 63 bidding route (p5–7).

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Capital cost and investment

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on hperc.org ↗

Report an issue with this document