HPERC · Himachal Pradesh Electricity Regulatory Commission

Promotion of Generation from Renewable Energy Sources and Tariff Determination (Third Amendment) Regulations, 2017

Himachal Pradesh Electricity Regulatory Commission (Promotion of Generation from the Renewable Energy Sources and Terms and Conditions for Tariff Determination) (Third Amendment) Regulations, 2017

AmendmentDated 31 Mar 2017In force from 1 Apr 2017No. HPERC/428 dated 31st March, 2017

Replaced by Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2017

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Promotion of Generation from Renewable Energy Sources and Tariff Determination Regulations, 2012.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on hperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Himachal Pradesh Electricity Regulatory Commission issued this notification at Shimla on 31 March 2017 (p1) as the Third Amendment to its 2012 renewable energy tariff-determination regulations. It takes effect on 1 April 2017 — the very date the previous control period was due to end (p1).

Four regulations do the work. Regulation 1 names the instrument and fixes commencement. Regulation 2 moves the date in Regulation 1(2) of the principal regulations from 31.03.2017 to 30.09.2017 (p1). Regulation 3 makes the same substitution in Regulation 9(1) and adds a proviso preserving the generic levellised tariffs already determined for small hydro projects for the control period, keeping them in force until 30 September 2017 unless amended or revoked earlier (p1). Regulation 4 substitutes the third proviso to Regulation 17(2), allowing the Commission to follow, mutatis mutandis, the Central Commission's technology-specific parameters — including capital cost — for smaller-capacity technologies, capped at 5 MW per technology; and adds a proviso to Regulation 17(3) permitting the Commission, by suo-moto order, to adopt the Central Commission's generic levellised tariff for any period and any renewable energy technology category other than SHPs (p1–2).

The practical effect is a six-month extension of the control period and of the small-hydro tariffs, plus a formal bridge to the CERC framework for other technologies.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff

Read with this

Voltaic last read HPERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document HPERC issued after the page that lists it was read may not be held by Voltaic yet.