Skip to content

PSERC · Punjab State Electricity Regulatory Commission

Electricity Supply Code, Standards of Performance and Related Matters, 2024 — 2nd Amendment Regulations, 2026 — Order

Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) (2nd Amendment) Regulations, 2026

OrderDated 25 Mar 2026

Read with the Electricity Supply Code, Standards of Performance and Related Matters Regulations, 2024.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is PSERC's reasoned order of 25.03.2026 disposing of stakeholder objections to the draft Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) (2nd Amendment) Regulations, 2026, and approving those regulations with one modification (p1, p3).

The amendment substitutes sub-regulation (16) of Regulation 41 of the principal Supply Code Regulations, 2024, on advance payment of electricity bills. The substituted text lets a consumer deposit advance payment of future bills, adjusted in succeeding months, and treats only amounts at or above a minimum threshold as advance payment — the threshold being the higher of the consumer's average bill for one billing cycle or a flat rupee amount, set at different levels for domestic supply and for other consumer categories (p1). The distribution licensee must keep issuing monthly or bimonthly bills showing the amount adjusted and the remaining advance balance, and must pay interest on the advance at the State Bank of India's one-month MCLR as on 1 April of the relevant financial year minus one percent, credited when the advance falls to zero or on 31 March, whichever is earlier (p1–2).

PSPCL was the only objector. It asked that the scheme be confined to DS/NRS/Industrial consumers with different threshold levels and that interest be capped, citing the 2021 cap in the earlier Supply Code and its own working-capital and MCLR data (p2–3). The Commission rejected the category restriction as discriminatory against other consumer classes and accepted the cap of 7.50%, directing that the interest rates apply from 01.04.2026 (p3).

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
Billing and payment, Conditions of supply

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗