Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) Regulations, 2024

OrderDated 23 Oct 2024

Made under the Electricity Supply Code, Standards of Performance and Related Matters Regulations, 2024.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software, from pages 1 to 36 of 142. Check the regulator's original before you rely on it.

This is PSERC's order dated 23.10.2024 disposing stakeholder objections to the draft Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) Regulations, 2024 (p1). It records that the draft and explanatory memorandum were issued for comments by 25.07.2024, a public hearing was held on 07.08.2024, fifteen stakeholders including PSPCL objected, and PSPCL replied by memo dated 12.09.2024 (p1–2).

The bulk of the supplied text is a clause-by-clause record of objections, PSPCL's reply, and the Commission's analysis and decision. The Commission settles definitions in Regulation 2 — Days, Distribution main, Essential services, Feeder, Franchisee, Housing Society, Industrial supply, Premises, Sanctioned/Contracted Load, Service Line and Temporary Connection — accepting some changes and rejecting others (p2–8). It amends certain definitions, including Industrial supply, Premises and Contracted Load, and confirms that street lights are not essential services (p5–7).

It then deals with general provisions in Regulations 4–7: amendment procedure, supply voltage and load limits, duty to supply, security, EV charging connections and general terms (p8–16). Decisions confirm that revised supply-voltage limits apply prospectively, that no amount is recoverable from existing 11 kV consumers paying voltage surcharge when converting under amended limits, that EV charging load cannot be clubbed with other loads, and that prepaid-meter security exemption is to be reflected in Regulation 6(12) (p12–15).

Later sections address application and load matters in Regulations 8–12: connected-load computation and Annexure-1, A&A forms, demand notices, proof of identity/ownership, NOCs, and colony/complex load planning norms (p16–36). The Commission retains the existing connected-load methodology, allows Aadhaar as identity proof, requires the licensee to give an A&A copy on demand, requires NOC lists within one month, and discusses developer/PSPCL issues on colony loads, system loading charges and land for substations (p16–36). Later parts are not available.

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
Conditions of supply, New connections and load changes, Standards of performance

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document