Electricity Supply Code, Standards of Performance and Related Matters, 2024 — 1st and 2nd Amendment, 2026 — Order

In the matter of Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) (1st Amendment) Regulations, 2026 And Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) (2nd Amendment) Regulations, 2026

OrderDated 17 Mar 2026

Read with the Electricity Supply Code, Standards of Performance and Related Matters Regulations, 2024.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a PSERC order of 17 March 2026 (p1, p16) disposing of stakeholder objections to two draft amendments to the Supply Code, 2024 notified in October 2024, and approving the first of them. Only PSPCL filed objections and appeared at the two public hearings (p1).

Section 2 (pp1–5) deals with the draft amendment to Regulation 49(2)(v) on treating demand above sanctioned or contracted load as unauthorized use of electricity. The Commission refuses PSPCL's proposed addition that the notice tell the consumer to get its load extended, accepts that UUE charges be computed pro rata on a 30-day billing cycle, clarifies adjustment of charges already paid for the cycle, holds that Regulation 49(3)(viii) does not apply to cases under the first proviso, and confirms the second to fourth provisos are unchanged (pp3–5).

Section 3 (pp5–16) covers the draft amendment on release of connections in abandoned colonies. The Commission rejects PSPCL's proposal to levy system loading and 11 kV connectivity charges on top of development charges, deciding residents pay only the service connection charges applicable to their category, or those plus development charges as specified; promoter liability is to be recovered from the promoter (pp11–13). It allows the three-month trigger to run from the date of past notices (pp15–16) and rejects several other PSPCL suggestions.

Section 4 (p16) records a correction to Regulation 12(8), where "distribution licensee" is to be read as "promoter", and then approves the Punjab State Electricity Regulatory Commission (Electricity Supply Code, Standards of Performance and Related Matters) (1st Amendment) Regulations, 2026 with the modifications discussed.

Standard name
Electricity Supply Code, Standards of Performance
Primary topics
Theft and unauthorised use, New connections and load changes, Connection and miscellaneous charges

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document