CERC · Central Electricity Regulatory Commission
Detailed Procedure for Ancillary Services Operations, 2016
Detailed Procedure For Ancillary Services Operations
ProcedureDate not stated
Replaced by Ancillary Services Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
Made under the Ancillary Services Operations Regulations, 2015.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the detailed operating procedure that NLDC (POSOCO) issued in March 2016 to give effect to the CERC (Ancillary Services Operations) Regulations, 2015 — expressly in compliance with Regulation 14 of those regulations (p3). It turns the parent regulations into an end-to-end workflow for Reserves Regulation Ancillary Services (RRAS): who may be called, what triggers a call, how it is scheduled and withdrawn, how energy is accounted for and how money moves.
Sections 1–3 set purpose and scope: the procedure binds generating stations that are Regional Entities whose full-capacity tariff is determined or adopted by CERC, plus SLDCs, RLDCs, NLDC and the RPCs, and excludes stations whose tariff is not so determined (p3–4).
Sections 4–7 allocate roles — NLDC as Nodal Agency (demand forecasting, merit-order stacks, dispatch through RLDCs, publication of variable costs and provider parameters), RRAS providers (monthly data and contact filings in Formats AS1 and AS2), RPCs (monthly publication of provider parameters in AS3 and preparation of energy/deviation accounts) and SLDCs (day-ahead block-wise demand forecast in AS4) (p4–8).
Sections 8–10 are the operational core: the event list permitting up- or down-regulation (weather, outages, n-1/ATC violations, load and frequency trends, area control error, loop flows, recall by the original beneficiary); how the two merit-order stacks are used; lead time and minimum dispatch durations for reserve-shutdown units; the earliest effective time block for a dispatch or withdrawal instruction; and curtailment priority, with RRAS ahead of STOA, MTOA and LTA (p9–15).
Sections 11–13 cover communication, weekly energy accounting alongside the DSM account, and settlement through each region's Deviation Settlement Pool, including payment priorities and interest for late payment (p15–18). Section 14 lets the Nodal Agency act in the interest of system operation with intimation to CERC, subject to later Commission-approved revision (p18). Seven prescribed formats, AS1–AS7, follow at pp19–25.
Read with this
The regulation
- Dated 13 Aug 2015Ancillary Services Operations Regulations, 2015
Commencement notices and reasons
Procedures and orders made under it
- Dated 21 Nov 2016Ancillary Services Operations — Detailed Procedure
- Dated 8 Dec 2016Corrigendum to Final Detailed Procedure for Ancillary Services Operations, 2016
Other copies of these documents (1)
- Dated 13 Aug 2015Ancillary Services Operations Regulations, 2015
Earlier drafts
- Dated 1 May 2015Ancillary Services Operations Regulations, 2015
- Released with the notice dated 1 May 2015Explanatory memorandum: Introduction of Ancillary Services in India — Explanatory Memorandum
- Dated 1 May 2015Public notice: Ancillary Services Operations Regulations, 2015 — Public Notice — Draft
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.