Skip to content

CERC · Central Electricity Regulatory Commission

Ancillary Services Operations — Detailed Procedure

Ancillary Services Operations Detailed Procedure

ProcedureDated 21 Nov 2016

Replaced by Ancillary Services Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Ancillary Services Operations Regulations, 2015.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Detailed Procedure for Ancillary Services Operations, issued to implement Regulation 14 of the CERC (Ancillary Services Operations) Regulations, 2015. It governs the Reserves Regulation Ancillary Services (RRAS) mechanism at inter-state level: how the Nodal Agency (NLDC) forecasts demand, builds merit-order stacks, dispatches RRAS providers through RLDCs, and how the service is scheduled, withdrawn, accounted and settled (p3–p4, p12–18).

Sections 1–3 set the basis, objective and scope: the procedure binds Regional Entities whose full-capacity tariff is determined or adopted by CERC, plus SLDCs, RLDCs, NLDC and RPCs, and applies to STOA/MTOA/LTA transactions; it excludes generating stations whose full-capacity tariff is not determined by CERC (p3–p4).

Sections 4–7 allocate roles. NLDC as Nodal Agency forecasts demand, prepares up/down merit-order stacks, monitors congestion and system parameters, directs RLDCs, publishes variable costs and merit order, and considers hydro peaking support (p4–p5). RRAS providers must submit generator data monthly in Format AS1 and contact details in Format AS2, follow dispatch instructions and maintain continuity (p6–p7). RPCs publish provider parameters monthly in Format AS3 and use them for energy/deviation accounts (p7–p8). SLDCs provide day-ahead block-wise demand forecasts in Format AS4 (p8).

Sections 8–10 are the operational core: triggering criteria for Regulation Up/Down (weather, outages, load trend, frequency band breaches with minimum duration, ACE trend, congestion, recall by original beneficiary, and other anticipated system conditions), merit-order dispatch rules for up and down regulation, lead times for reserve-shutdown units, exclusions for small URS, scheduling through a Virtual Ancillary Entity per regional grid, withdrawal criteria, and treatment of deviations under the CERC DSM Regulations, 2014 (p8–15).

Sections 11–14 cover communication, weekly energy accounting alongside DSM accounts, RRAS settlement through regional DSM pool accounts (fixed and variable charges, mark-up, refunds to original beneficiaries, payment timelines and interest), and removal of difficulties with Nodal Agency/RLDC decisions and review with CERC approval (p15–19).

The annexures provide seven formats for data submission, despatch instructions, withdrawal and weekly settlement (p20–27). The procedure takes effect from the date of CERC approval.

Standard name
Ancillary Services Regulations
Primary topics
Ancillary services and reserves, Scheduling and despatch, Energy accounting and settlement

Read with this

The regulation

Commencement notices and reasons

Other copies of these documents (1)

Earlier drafts

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document