CERC · Central Electricity Regulatory Commission
Ancillary Services Operations Regulations, 2015
Central Electricity Regulatory Commission (Ancillary Services Operations) Regulations, 2015
Regulation · Gazette copyDated 13 Aug 2015Published in the Gazette 19 Aug 2015No. 18/1/2013/Reg.Aff.(AS Regul.)/CERC. dated 13th August, 2015
Replaced by Ancillary Services Regulations, 2022
See that regulation for the date it took effect and for anything it keeps in force.
The Gazette copy of the Ancillary Services Operations Regulations, 2015.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action taken or purported to have been done or taken including any procedure, minutes, reports, confirmation or declaration of any instrument executed under the repealed regulations shall be deemed to have been done or taken under the relevant provisions of these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Central Electricity Regulatory Commission's Ancillary Services Operations Regulations, 2015 were notified at New Delhi on 13 August 2015 (p6) and published in the Gazette of India on 19 August 2015 (p1). Made under section 178 of the Electricity Act, 2003 (p6), they create the Reserves Regulation Ancillary Services (RRAS) framework and apply to regional entities transacting through short-, medium- or long-term open access in inter-state transmission (p7).
Regulations 1–4 set commencement (to be separately notified), definitions of the machinery — RRAS, Regulation Up and Regulation Down, the RRAS Provider, the Virtual Ancillary Entity, un-requisitioned surplus, deviation, congestion and the Nodal Agency — and state the objective of restoring frequency and relieving transmission congestion (p6–7).
Regulations 5–8 allocate roles: every regional generating station whose tariff the Commission determines or adopts for its full capacity must provide RRAS; the Nodal Agency (NLDC through the RLDCs, with SLDCs at intra-state level when SERCs introduce the service) builds merit-order stacks of un-requisitioned surplus for Regulation Up and a separate stack for Regulation Down, factoring ramp rates, response time and transmission congestion, and triggers despatch on listed system events; providers submit charges monthly to the Regional Power Committees, which feed those charges into merit order and energy accounts (p7–8).
Regulations 9–13 are the operational core: scheduling of dispatched quantum to the Virtual Ancillary Entity, deemed triggering and withdrawal, treatment of deviations under the Deviation Settlement Mechanism Regulations 2014, weekly energy accounting by RPCs with an Ancillary Services Statement, and settlement through the Regional Deviation Pool Account Fund, including payment principles for Regulation Up, payback for Regulation Down, a bar on retrospective revision of charges and penalties for sustained failure or gaming (p8–9).
Regulations 14–16 leave operational detail to a Detailed Procedure to be issued by the Nodal Agency within three months with the Commission's prior approval, and reserve the Commission's powers to relax provisions and issue directions (p9).
Read with this
The regulation
- Dated 13 Aug 2015Ancillary Services Operations Regulations, 2015
Commencement notices and reasons
Procedures and orders made under it
- Dated 21 Nov 2016Ancillary Services Operations — Detailed Procedure
- Dated 8 Dec 2016Corrigendum to Final Detailed Procedure for Ancillary Services Operations, 2016
- Date not statedDetailed Procedure for Ancillary Services Operations, 2016
Earlier drafts
- Dated 1 May 2015Ancillary Services Operations Regulations, 2015
- Released with the notice dated 1 May 2015Explanatory memorandum: Introduction of Ancillary Services in India — Explanatory Memorandum
- Dated 1 May 2015Public notice: Ancillary Services Operations Regulations, 2015 — Public Notice — Draft
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.