UERC · Uttarakhand Electricity Regulatory Commission
RE Tariff Regulations, 2023 — First Amendment, 2024 — Statement of Reasons
UERC (Tariff and Other Terms for Supply of Electricity from Renewable Energy Sources and non-fossil fuel based Co-generating Stations) (First Amendment) Regulations, 2024.
Statement of reasonsDate not stated
The commission's reasons for the RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023 or one of its amendments.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Statement of Reasons accompanying the UERC First Amendment Regulations, 2024 to the 2023 RE tariff regulations. It records why the Commission revised the Renewable Purchase Obligation framework and the rooftop/small solar provisions, then reproduces the final amended text. Pages 1–2 set out the background: the Principal Regulations were notified on 26 August 2023; MoP revised the RPO trajectory on 20 October 2023; MNRE and MoP letters pushed distribution licensees to plan for renewable consumption norms and to follow consumer-rule timelines for rooftop solar. The draft amendments covered Regulation 10 (RPO) and Regulation 37 (grid-interactive rooftop and small solar PV). Pages 2–4 reproduce the draft Regulation 10, including an annual RPO trajectory table, wind/hydro/distributed/other RPO categories, eligibility dates for wind and hydro projects, the distributed-RPO multiplier where generation data is missing, and an energy storage obligation table. Pages 5–11 record stakeholder comments and the Commission’s decisions, including rejection of a separate solar or biomass RPO, rejection of Pump Storage Plants under the storage obligation, and rejection of adjusting distributed RPO against other RPO. The final Regulation 10 is then reproduced, with Wind RPO eligibility moved to projects commissioned after 31 March 2022. Pages 11–14 cover Regulation 37: comments on feasibility studies, load enhancement and infrastructure costs, followed by the final rooftop/small solar provisions on capacity caps, net-energy settlement, payment for net injection, deemed generation, augmentation, virtual net metering, and timelines for feasibility study and commissioning. Pages 14–16 record UJVN Ltd.’s request to raise the Virtual/Group Net Metering ceiling, which the Commission rejects. No date of issuance or Gazette publication is printed in the text.
Read with this
The regulation
- Dated 16 Aug 2023RE and Non-Fossil Fuel Co-generation Tariff Regulations, 2023
Amendments and corrections
- Dated 20 Jun 2024RE Tariff Regulations, 2023 — First Amendment, 2024
- Dated 27 Nov 2025RE Tariff Regulations, 2023 — Second Amendment, 2025
Commencement notices and reasons
Proposed changes (drafts with no final yet)
- Dated 12 Jun 2025Solar PV, Solar Thermal and Grid Interactive Rooftop & Small Solar PV Benchmark Capital Cost Review, FY 2025-26 — Draft
- Released with the draft dated 12 Jun 2025Public notice: Public Notice — Draft Solar Benchmark Capital Cost Review Order, FY 2025-26
8 more documents belong here and are not on Voltaic: 3 copies in another language, 3 drafts or notices on a draft and 2 drafts or notices on a draft not held as English text.
Voltaic last read UERC's website for final documents on 24 Nov 2026. A document UERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.